🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Oregon

SOLAR · WEST

Solar project 850, Crook County

Solar project 850, Crook County is a 60.8 MW solar request built and operating in the West interconnection queue, in Crook County, Oregon, connecting to PacifiCorp.

Queue statusOperating
  1. PlanningQueued Feb 2017 (completed)
  2. ConsentedApr 2019 (completed)
  3. Construction (completed)
  4. OperatingTarget Feb 2021 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
850
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
Millican Solar Energy LLC
Connection point (POI)
Ponderosa-Houston Lake transmission line
Location
Crook County, Oregon
Technology
Solar: 60.8 MW
Total requested
60.8 MW
Service type
Energy only (ERIS)
Study phase
IA executed 4/30/19
Queue status
Operational
Entered queue
8 February 2017
Agreement signed
30 April 2019
Proposed online date
February 2021

Location

Marker shows the centre of Crook County; the queue data does not give exact sites.

Power plants in Oregon · Transmission lines in Oregon

Other requests in Crook County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem