ONSHORE WIND · WEST

Klondike 3 Wind

Klondike 3 Wind is a 300 MW onshore wind request built and operating in the West interconnection queue, in Wasco County, Oregon, connecting to Klondike Wind Power III, LLC.

Queue statusOperating
  1. PlanningQueued Feb 2004 (completed)
  2. ConsentedNov 2006 (completed)
  3. Construction (completed)
  4. OperatingTarget Oct 2007 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
G124
Grid region
West (non-ISO utilities)
Utility / transmission owner
Klondike Wind Power III, LLC
Developer
Klondike Wind Power III, LLC
Connection point (POI)
Klondike Schoolhouse 230kV
Location
Wasco County, Oregon
Technology
Wind: 300 MW
Total requested
300 MW
Service type
Energy only (ERIS)
Study phase
IA Executed
Queue status
Operational
Entered queue
12 February 2004
Agreement signed
8 November 2006
Proposed online date
October 2007

Location

Marker shows the centre of Wasco County; the queue data does not give exact sites.

Power plants in Oregon · Transmission lines in Oregon

Other requests in Wasco County