Biglow Canyon Wind

Biglow Canyon Wind is a 600 MW onshore wind request built and operating in the West interconnection queue, in Sherman County, Oregon, connecting to Portland General Electric Company.

Queue statusOperating
  1. PlanningQueued Apr 2002 (completed)
  2. ConsentedNov 2006 (completed)
  3. Construction (completed)
  4. OperatingTarget Dec 2008 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
G99
Grid region
West (non-ISO utilities)
Utility / transmission owner
Portland General Electric Company
Connection point (POI)
Biglow Canyon
Location
Sherman County, Oregon
Technology
Wind: 600 MW
Total requested
600 MW
Service type
Energy only (ERIS)
Study phase
PGE acquired 400 MWs of interconnection rights, executed an LGIA and have energized a 400 MW wind project. The other 200
Queue status
Operational
Entered queue
5 April 2002
Agreement signed
6 November 2006
Proposed online date
December 2008

Location

Marker shows the centre of Sherman County; the queue data does not give exact sites.