United States โ€บ Grid โ€บ Interconnection queues โ€บ Oklahoma

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in Oklahoma (2023 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown8215.6 GW
Active in queue5,119 MW34 requests
Agreement signed262 MW3 requests
Withdrawn8215.6 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

82 requests ยท page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project GEN-2022-107, Tillman County
Solar
400 MWWithdrawn / abandoned Tillman, OKSPP Jan 2023target 2026
Solar project GEN-2022-228, Logan County
Solar
335 MWWithdrawn / abandoned Logan, OKSPP Feb 2023target 2028
Solar project GEN-2022-224, Muskogee County
Solar
325 MWWithdrawn / abandoned Muskogee, OKSPP Feb 2023target 2028
Solar project GEN-2022-126, Caddo County
Solar
305 MWWithdrawn / abandoned Caddo, OKSPP Feb 2023target 2028
Battery storage project GEN-2022-138, Roger Mills County
Battery storage
300 MWWithdrawn / abandoned Roger Mills, OKSPP Feb 2023target 2027
Solar project GEN-2022-106, Tillman County
Solar
300 MWWithdrawn / abandoned Tillman, OKSPP Jan 2023target 2026
Battery storage project GEN-2022-132, Caddo County
Battery storage
300 MWWithdrawn / abandoned Caddo, OKSPP Feb 2023target 2027
Solar project GEN-2022-105, Tillman County
Solar
300 MWWithdrawn / abandoned Tillman, OKSPP Jan 2023target 2026
Solar + storage project GEN-2023-100, Woods County
Solar + storage
300 MWWithdrawn / abandoned Woods, OKSPP Oct 2023target 2027
Onshore wind project GEN-2023-134, Hughes County
Onshore wind
252 MWWithdrawn / abandoned Hughes, OKSPP Oct 2023target 2026
Solar project GEN-2022-167, Tulsa County
Solar
250 MWWithdrawn / abandoned Tulsa, OKSPP Feb 2023target 2028
Battery storage project GEN-2023-009, Haskell County
Battery storage
250 MWWithdrawn / abandoned Haskell, OKSPP Oct 2023target 2028
Solar project GEN-2023-179, Craig County
Solar
250 MWWithdrawn / abandoned Craig, OKSPP Oct 2023target 2030
Onshore wind project GEN-2023-138, Delaware County
Onshore wind
250 MWWithdrawn / abandoned Delaware, OKSPP Oct 2023target 2028
Onshore wind project GEN-2023-022, Mcintosh County
Onshore wind
250 MWWithdrawn / abandoned Mcintosh, OKSPP Oct 2023target 2027
Other project GEN-2023-211, Kay County
Other
250 MWWithdrawn / abandoned Kay, OKSPP Oct 2023target 2028
Onshore wind project GEN-2023-072, Delaware County
Onshore wind
250 MWWithdrawn / abandoned Delaware, OKSPP Oct 2023target 2028
Battery storage project GEN-2023-167, Oklahoma County
Battery storage
250 MWWithdrawn / abandoned Oklahoma, OKSPP Oct 2023target 2028
Onshore wind project GEN-2022-114, Tillman County
Onshore wind
250 MWWithdrawn / abandoned Tillman, OKSPP Feb 2023target 2027
Onshore wind project GEN-2022-115, Tillman County
Onshore wind
250 MWWithdrawn / abandoned Tillman, OKSPP Feb 2023target 2026
Other project GEN-2023-SR21, Oklahoma County
Other
235 MWWithdrawn / abandoned Oklahoma, OKSPP Mar 2023target 2026
Solar + storage project GEN-2023-028, Mayes County
Solar + storage
230 MWWithdrawn / abandoned Mayes, OKSPP Oct 2023target 2028
Battery storage project GEN-2022-182, Tillman County
Battery storage
225 MWWithdrawn / abandoned Tillman, OKSPP Feb 2023target 2026
Battery storage project GEN-2022-183, Tillman County
Battery storage
225 MWWithdrawn / abandoned Tillman, OKSPP Feb 2023target 2026
Solar project GEN-2022-179, Tillman County
Solar
225 MWWithdrawn / abandoned Tillman, OKSPP Feb 2023target 2026
Solar project GEN-2022-178, Tillman County
Solar
225 MWWithdrawn / abandoned Tillman, OKSPP Feb 2023target 2026
Solar project GEN-2023-020, Marshall County
Solar
220 MWWithdrawn / abandoned Marshall, OKSPP Oct 2023target 2026
Onshore wind project GEN-2022-196, Pittsburg County
Onshore wind
215 MWWithdrawn / abandoned Pittsburg, OKSPP Feb 2023target 2027
Onshore wind project GEN-2023-053, Pittsburg County
Onshore wind
212 MWWithdrawn / abandoned Pittsburg, OKSPP Oct 2023target 2028
Battery storage project GEN-2023-164, Caddo County
Battery storage
210 MWWithdrawn / abandoned Caddo, OKSPP Oct 2023target 2028
Battery storage project GEN-2023-165, Caddo County
Battery storage
210 MWWithdrawn / abandoned Caddo, OKSPP Oct 2023target 2028
Onshore wind project GEN-2023-003, Hughes County
Onshore wind
201 MWWithdrawn / abandoned Hughes, OKSPP Jul 2023target 2026
Battery storage project GEN-2023-019, Tillman County
Battery storage
200 MWWithdrawn / abandoned Tillman, OKSPP Oct 2023target 2026
Battery storage project GEN-2022-137, Cleveland County
Battery storage
200 MWWithdrawn / abandoned Cleveland, OKSPP Feb 2023target 2027
Onshore wind project GEN-2023-075, Nowata County
Onshore wind
200 MWWithdrawn / abandoned Nowata, OKSPP Oct 2023target 2027
Solar project GEN-2022-180, Tillman County
Solar
200 MWWithdrawn / abandoned Tillman, OKSPP Feb 2023target 2026
Battery storage project GEN-2022-226, Muskogee County
Battery storage
200 MWWithdrawn / abandoned Muskogee, OKSPP Feb 2023target 2028
Solar project GEN-2022-157, Texas County
Solar
200 MWWithdrawn / abandoned Texas, OKSPP Feb 2023target 2028
Battery storage project GEN-2022-230, Logan County
Battery storage
200 MWWithdrawn / abandoned Logan, OKSPP Feb 2023target 2028
Battery storage project GEN-2023-SR11, Beaver County
Battery storage
200 MWWithdrawn / abandoned Beaver, OKSPP Feb 20232025
Battery storage project GEN-2022-229, Logan County
Battery storage
200 MWWithdrawn / abandoned Logan, OKSPP Feb 2023target 2028
Solar + storage project GEN-2023-131, Muskogee County
Solar + storage
200 MWWithdrawn / abandoned Muskogee, OKSPP Oct 2023target 2027
Battery storage project GEN-2022-225, Muskogee County
Battery storage
200 MWWithdrawn / abandoned Muskogee, OKSPP Feb 2023target 2028
Battery storage project GEN-2022-129, Osage County
Battery storage
200 MWWithdrawn / abandoned Osage, OKSPP Feb 2023target 2027
Solar project GEN-2022-181, Tillman County
Solar
200 MWWithdrawn / abandoned Tillman, OKSPP Feb 2023target 2026
Battery storage project GEN-2022-163, Canadian County
Battery storage
200 MWWithdrawn / abandoned Canadian, OKSPP Feb 2023target 2026
Solar project GEN-2022-234, Rogers County
Solar
200 MWWithdrawn / abandoned Rogers, OKSPP Feb 2023target 2028
Battery storage project GEN-2023-103, Rogers County
Battery storage
200 MWWithdrawn / abandoned Rogers, OKSPP Oct 2023target 2027
Solar + storage project GEN-2023-156, Jefferson County
Solar + storage
200 MWWithdrawn / abandoned Jefferson, OKSPP Oct 2023target 2028
Solar project GEN-2023-041, Mcintosh County
Solar
190 MWWithdrawn / abandoned Mcintosh, OKSPP Oct 2023target 2030
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)