Other project GEN-2023-SR21, Oklahoma County

Other project GEN-2023-SR21, Oklahoma County is a 235 MW other request withdrawn in the SPP interconnection queue, in Oklahoma County, Oklahoma, connecting to OGE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2023 (completed)
  2. Withdrawn / abandonedSep 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2023-SR21
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
OGE
Connection point (POI)
138 KV substation at Horeshoe Lake, specifically Horseshoe Lake 7 (OKGEHL7)
Location
Oklahoma County, Oklahoma
Technology
Other: 235 MW
Total requested
235 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
24 March 2023
Proposed online date
May 2026
Withdrawn
September 2023

Location

Marker shows the centre of Oklahoma County; the queue data does not give exact sites.