United States βΊ Grid βΊ Interconnection queues βΊ Oklahoma
ONSHORE WIND Β· SPPOnshore wind project GEN-2023-022, Mcintosh County
Onshore wind project GEN-2023-022, Mcintosh County is a 250 MW onshore wind request withdrawn in the SPP interconnection queue, in Mcintosh County, Oklahoma, connecting to OGE.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2023 (completed)
- Withdrawn / abandonedAug 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2023-022
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- OGE
- Connection point (POI)
- Canadian River 345 kV Substation
- Location
- Mcintosh County, Oklahoma
- Technology
- Wind: 250 MW
- Total requested
- 250 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 2 October 2023
- Proposed online date
- December 2027
- Withdrawn
- August 2025
Location
Marker shows the centre of Mcintosh County; the queue data does not give exact sites.
Other requests in Mcintosh County
- Solar project GEN-2024-297, Mcintosh CountySolar Β· 167 MW Β· in study
- Solar project GEN-2024-296, Mcintosh CountySolar Β· 167 MW Β· in study
- Solar project GEN-2024-298, Mcintosh CountySolar Β· 167 MW Β· in study
- Onshore wind project GEN-2022-074, Mcintosh CountyOnshore wind Β· 221 MW Β· withdrawn
- Solar project GEN-2023-041, Mcintosh CountySolar Β· 190 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem