United States β€Ί Grid β€Ί Interconnection queues β€Ί Ohio

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Ohio (2011 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown253,272 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn253,272 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

25 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project X3-051
Gas
610 MWWithdrawn / abandoned OHPJM Sep 2011target 2017
Emerson Creek Wind Farm
Onshore wind
500 MWWithdrawn / abandoned Huron, OHPJM Mar 2011target 2018
Onshore wind project J208, Huron County
Onshore wind
500 MWWithdrawn / abandoned Huron, OHMISO Mar 2011target 2014
Gas project X1-064A_AT13, Summit County
Gas
268 MWWithdrawn / abandoned Summit, OHPJM Apr 2011target 2014
Gas project J211, Summit County
Gas
268 MWWithdrawn / abandoned Summit, OHMISO Apr 2011target 2013
Onshore wind project X3-030, Marion County
Onshore wind
245 MWWithdrawn / abandoned Marion, OHPJM Aug 2011target 2015
Coal project X1-027, Scioto County
Coal
200 MWWithdrawn / abandoned Scioto, OHPJM Mar 2011target 2014
Onshore wind project X3-031, Allen County
Onshore wind
150 MWWithdrawn / abandoned Allen, OHPJM Aug 2011target 2015
Onshore wind project X2-058, Hancock County
Onshore wind
150 MWWithdrawn / abandoned Hancock, OHPJM Jun 2011target 2012
Onshore wind project X2-039, Ashland County
Onshore wind
100 MWWithdrawn / abandoned Ashland, OHPJM Jun 2011target 2013
6011 Greenwich Windpark, LLC
Onshore wind
60.0 MWWithdrawn / abandoned Huron, OHPJM Aug 2011target 2017
Gas project X4-003, Washington County
Gas
56.0 MWWithdrawn / abandoned Washington, OHPJM Nov 2011target 2015
Solar project X1-009, Allen County
Solar
20.0 MWWithdrawn / abandoned Allen, OHPJM Feb 2011target 2012
Solar project J210, Butler County
Solar
20.0 MWWithdrawn / abandoned Butler, OHMISO Apr 2011target 2013
Solar project X1-058A_DK2, Butler County
Solar
20.0 MWWithdrawn / abandoned Butler, OHPJM Apr 2011target 2012
Solar project X3-059, Marion County
Solar
20.0 MWWithdrawn / abandoned Marion, OHPJM Oct 2011target 2012
Solar project X3-053, Medina County
Solar
17.7 MWWithdrawn / abandoned Medina, OHPJM Sep 2011target 2013
Barberton Solar
Solar
14.0 MWWithdrawn / abandoned Summit, OHPJM Jul 2011target 2014
Solar project X4-030, Sandusky County
Solar
13.8 MWWithdrawn / abandoned Sandusky, OHPJM Dec 2011target 2013
Solar project X1-033, Wyandot County
Solar
12.0 MWWithdrawn / abandoned Wyandot, OHPJM Mar 2011target 2012
Solar project X2-077, Darke County
Solar
10.0 MWWithdrawn / abandoned Darke, OHPJM Jul 2011target 2013
Other project X2-053, Jefferson County
Other
6.4 MWWithdrawn / abandoned Jefferson, OHPJM Jun 2011target 2013
Solar project X2-051
Solar
6.0 MWWithdrawn / abandoned OHPJM Jun 2011
Greenville Solar
Solar
3.4 MWWithdrawn / abandoned Darke, OHPJM Aug 2011target 2017
Edgewood
Solar
1.8 MWWithdrawn / abandoned Hancock, OHPJM Aug 2011target 2014

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)