United States β€Ί Grid β€Ί Interconnection queues β€Ί North Dakota

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in North Dakota (2025 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown205,528 MW
Active in queue5,528 MW20 requests
Agreement signed0.0 MW0 requests
Withdrawn61,130 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

20 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project ERAS-2025-012, Mercer County
Gas
750 MWIn study Mercer, NDSPP Oct 2025target 2030
Gas project ERAS-2025-011, Mercer County
Gas
750 MWIn study Mercer, NDSPP Oct 2025target 2030
Solar + storage project J4105, Cass County
Solar + storage
500 MWIn study Cass, NDMISO Oct 2025target 2028
Solar + storage project J4106, Cass County
Solar + storage
500 MWIn study Cass, NDMISO Oct 2025target 2027
Red Butte Wind
Onshore wind Β· Red Butte Wind, LLC
457 MWIn study Morton, NDMISO Aug 2025target 2028
Onshore wind project GEN-2024-141, Mercer County
Onshore wind
424 MWIn study Mercer, NDSPP Mar 2025target 2031
Battery storage project GEN-2024-331, Dunn County
Battery storage
300 MWIn study Dunn, NDSPP Mar 2025target 2028
Battery storage project GEN-2024-328, Slope County
Battery storage
250 MWIn study Slope, NDSPP Mar 2025target 2028
Battery storage project GEN-2024-326, Stark County
Battery storage
225 MWIn study Stark, NDSPP Mar 2025target 2028
Battery storage project MPC04600, Eddy County
Battery storage
209 MWIn study Eddy, NDMISO Nov 2025target 2028
Battery storage project GEN-2024-329, Williams County
Battery storage
200 MWIn study Williams, NDSPP Mar 2025target 2028
Battery storage project GEN-2024-327, Ward County
Battery storage
200 MWIn study Ward, NDSPP Mar 2025target 2028
Surplus; J1588
Battery storage
200 MWIn study Cass, NDMISO Mar 2025target 2028
Solar project GEN-2024-284, Mercer County
Solar
199 MWIn study Mercer, NDSPP Mar 2025target 2028
Solar + storage project J4170, Richland County
Solar + storage
172 MWIn study Richland, NDMISO Oct 2025target 2029
Battery storage project GEN-2024-359, Stark County
Battery storage
100 MWIn study Stark, NDSPP Mar 2025target 2030
Solar project J4077, Emmons County
Solar
45.0 MWIn study Emmons, NDMISO Oct 2025target 2030
Solar project J4070, Emmons County
Solar
40.0 MWIn study Emmons, NDMISO Oct 2025target 2030
Onshore wind project GEN-2025-GR5, Ward County
Onshore wind
7.7 MWIn study Ward, NDSPP Oct 2025
Onshore wind project GEN-2025-GR3, Mclean County
Onshore wind
0.0 MWIn study Mclean, NDSPP Oct 2025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)