United States โ€บ Grid โ€บ Interconnection queues โ€บ New Mexico

OCTARY USA ยท INTERCONNECTION QUEUES

Interconnection queue in New Mexico (2025 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5813.4 GW
Active in queue13.4 GW58 requests
Agreement signed0.0 MW0 requests
Withdrawn288,099 MW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

58 requests ยท page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project IA-PNM-2025-10, Bernalillo County
Solar + storage
800 MWIn study Bernalillo, NMWest Mar 2025target 2028
Solar + storage project GEN-2024-303, Roosevelt County
Solar + storage
500 MWIn study Roosevelt, NMSPP Mar 2025target 2029
Solar + storage project GEN-2024-304, Roosevelt County
Solar + storage
500 MWIn study Roosevelt, NMSPP Mar 2025target 2029
Solar + storage project GEN-2024-124, Lea County
Solar + storage
420 MWIn study Lea, NMSPP Mar 2025target 2028
Battery storage project IA-PNM-2025-09, Valencia County
Battery storage
400 MWIn study Valencia, NMWest Mar 2025target 2029
Solar + storage project ERAS-2025-020, Lea County
Solar + storage
400 MWIn study Lea, NMSPP Oct 2025target 2030
Onshore wind project GEN-2024-221, Roosevelt County
Onshore wind
400 MWIn study Roosevelt, NMSPP Mar 2025target 2030
Onshore wind project IA-PNM-2025-19, Torrance County
Onshore wind
400 MWIn study Torrance, NMWest Mar 2025target 2028
Va400B
Battery storage
400 MWIn study Dona Ana, NMWest Jun 2025target 2028
Solar + storage project IA-PNM-2025-01, Valencia County
Solar + storage
371 MWIn study Valencia, NMWest Jan 2025target 2030
Solar + storage project ERAS-2025-030, Chaves County
Solar + storage
350 MWIn study Chaves, NMSPP Oct 2025target 2030
WMA300SB
Solar + storage
300 MWIn study Sierra, NMWest May 2025target 2029
Solar project GEN-2024-159, Roosevelt County
Solar
300 MWIn study Roosevelt, NMSPP Mar 2025target 2029
Es300B
Battery storage
300 MWIn study Otero, NMWest Jun 2025target 2028
Wind + storage project GEN-2024-278, Lea County
Wind + storage
264 MWIn study Lea, NMSPP Mar 2025target 2029
Solar + storage project ERAS-2025-018, Roosevelt County
Solar + storage
256 MWIn study Roosevelt, NMSPP Oct 2025target 2030
Solar + storage project IA-PNM-2025-04, Bernalillo County
Solar + storage
250 MWIn study Bernalillo, NMWest Mar 2025target 2028
Other project Q610, San Juan County
Other
250 MWIn study San Juan, NMWest May 2025target 2029
Onshore wind project IA-PNM-2025-18, Torrance County
Onshore wind
250 MWIn study Torrance, NMWest Mar 2025target 2028
Solar + storage project GEN-2024-271, Chaves County
Solar + storage
250 MWIn study Chaves, NMSPP Mar 2025target 2029
Solar + storage project GEN-2024-281, Lea County
Solar + storage
250 MWIn study Lea, NMSPP Mar 2025target 2029
Battery storage project GEN-2024-371, Lea County
Battery storage
250 MWIn study Lea, NMSPP Mar 2025target 2028
Solar + storage project IA-PNM-2025-06, Bernalillo County
Solar + storage
250 MWIn study Bernalillo, NMWest Mar 2025target 2031
Solar project GEN-2024-311, Chaves County
Solar
225 MWIn study Chaves, NMSPP Mar 2025target 2030
Solar + storage project IA-PNM-2025-05, Bernalillo County
Solar + storage
225 MWIn study Bernalillo, NMWest Mar 2025target 2030
Battery storage project GI-SISS-2025-03, Mckinley County
Battery storage
200 MWIn study Mckinley, NMWest Jul 2025target 2027
Onshore wind project GEN-2024-365, Lea County
Onshore wind
200 MWIn study Lea, NMSPP Mar 2025target 2030
LD200SB
Solar + storage
200 MWIn study Luna, NMWest Jun 2025target 2028
Onshore wind project GEN-2024-366, Lea County
Onshore wind
200 MWIn study Lea, NMSPP Mar 2025target 2030
Battery storage project GEN-2024-246, Eddy County
Battery storage
199 MWIn study Eddy, NMSPP Mar 2025target 2029
Solar + storage project IA-PNM-2025-02, Valencia County
Solar + storage
199 MWIn study Valencia, NMWest Jan 2025target 2030
Onshore wind project GI-CS-2025-18, Union County
Onshore wind
199 MWIn study Union, NMWest Sep 2025target 2029
Me199SB
Solar + storage
199 MWIn study Luna, NMWest Jun 2025target 2028
Solar + storage project GEN-2024-351, Lea County
Solar + storage
199 MWIn study Lea, NMSPP Mar 2025target 2029
Battery storage project GEN-2024-186, Chaves County
Battery storage
199 MWIn study Chaves, NMSPP Mar 2025target 2029
Me195SB
Solar + storage
195 MWIn study Luna, NMWest Jun 2025target 2029
Ve-DL-195SB
Solar + storage
195 MWIn study Dona Ana, NMWest May 2025target 2028
Onshore wind project IA-PNM-2025-15, Mckinley County
Onshore wind
190 MWIn study Mckinley, NMWest Mar 2025target 2030
Gas project IA-PNM-2025-20, Bernalillo County
Gas
172 MWIn study Bernalillo, NMWest Mar 2025target 2029
Battery storage project GEN-2024-324, Chaves County
Battery storage
160 MWIn study Chaves, NMSPP Mar 2025target 2028
Gas project ERAS-2025-014, Lea County
Gas
160 MWIn study Lea, NMSPP Oct 2025target 2029
Solar + storage project GEN-2024-265, Lea County
Solar + storage
155 MWIn study Lea, NMSPP Mar 2025target 2029
Solar + storage project GEN-2024-261, Lea County
Solar + storage
150 MWIn study Lea, NMSPP Mar 2025target 2029
Battery storage project GEN-2024-325, Chaves County
Battery storage
150 MWIn study Chaves, NMSPP Mar 2025target 2028
Battery storage project IA-PNM-2025-13, Valencia County
Battery storage
150 MWIn study Valencia, NMWest Mar 2025target 2027
Battery storage project GEN-2024-306, Lea County
Battery storage
150 MWIn study Lea, NMSPP Mar 2025target 2031
Ve-DL-150SB
Solar + storage
150 MWIn study Dona Ana, NMWest Jun 2025target 2028
Battery storage project GEN-2024-251, Eddy County
Battery storage
125 MWIn study Eddy, NMSPP Mar 2025target 2029
Onshore wind project GEN-2025-GR2, Roosevelt County
Onshore wind
120 MWIn study Roosevelt, NMSPP Jun 2025
Battery storage project GEN-2024-295, Eddy County
Battery storage
115 MWIn study Eddy, NMSPP Mar 2025target 2030
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)