United States β€Ί Grid β€Ί Interconnection queues β€Ί New Mexico

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in New Mexico (2023 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown408,600 MW
Active in queue3,383 MW15 requests
Agreement signed624 MW3 requests
Withdrawn408,600 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

40 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project GEN-2023-095, Quay County
Solar
850 MWWithdrawn / abandoned Quay, NMSPP Oct 2023target 2028
Solar + storage project GEN-2023-081, Lea County
Solar + storage
625 MWWithdrawn / abandoned Lea, NMSPP Oct 2023target 2028
Solar + storage project C3-137, San Juan County
Solar + storage
450 MWWithdrawn / abandoned San Juan, NMWest May 2023target 2027
Solar + storage project IA-PNM-2023-20, San Juan County
Solar + storage
400 MWWithdrawn / abandoned San Juan, NMWest Sep 2023target 2028
Solar project GEN-2023-236, Lea County
Solar
400 MWWithdrawn / abandoned Lea, NMSPP Oct 2023target 2030
Battery storage project IA-PNM-2023-25, Bernalillo County
Battery storage
350 MWWithdrawn / abandoned Bernalillo, NMWest Sep 2023target 2028
Solar + storage project GEN-2023-203, Lea County
Solar + storage
300 MWWithdrawn / abandoned Lea, NMSPP Oct 2023target 2028
Solar + storage project GEN-2023-201, Lea County
Solar + storage
300 MWWithdrawn / abandoned Lea, NMSPP Oct 2023target 2028
Solar + storage project IA-PNM-2023-12, San Juan County
Solar + storage
298 MWWithdrawn / abandoned San Juan, NMWest Jan 2023target 2027
Onshore wind project GEN-2022-159, Chaves County
Onshore wind
280 MWWithdrawn / abandoned Chaves, NMSPP Feb 2023target 2027
Onshore wind project GEN-2022-160, Chaves County
Onshore wind
280 MWWithdrawn / abandoned Chaves, NMSPP Feb 2023target 2028
Solar + storage project IA-PNM-2023-21, San Juan County
Solar + storage
250 MWWithdrawn / abandoned San Juan, NMWest Sep 2023target 2028
Solar project GEN-2023-001, Lea County
Solar
230 MWWithdrawn / abandoned Lea, NMSPP May 20232025
Onshore wind project GEN-2022-171, Curry County
Onshore wind
200 MWWithdrawn / abandoned Curry, NMSPP Feb 2023target 2026
Battery storage project GEN-2022-233, Curry County
Battery storage
200 MWWithdrawn / abandoned Curry, NMSPP Feb 2023target 2028
Solar project GEN-2023-178, Roosevelt County
Solar
200 MWWithdrawn / abandoned Roosevelt, NMSPP Oct 2023target 2026
Solar project GEN-2022-232, Curry County
Solar
200 MWWithdrawn / abandoned Curry, NMSPP Feb 2023target 2028
Solar project GEN-2023-184, Eddy County
Solar
200 MWWithdrawn / abandoned Eddy, NMSPP Oct 2023target 2030
Solar + storage project IA-PNM-2023-24, Hidalgo County
Solar + storage
200 MWWithdrawn / abandoned Hidalgo, NMWest Sep 2023target 2028
Battery storage project IA-PNM-2023-26, Luna County
Battery storage
200 MWWithdrawn / abandoned Luna, NMWest Sep 2023target 2026
Solar + storage project IA-PNM-2023-27, San Juan County
Solar + storage
199 MWWithdrawn / abandoned San Juan, NMWest Sep 2023target 2028
Solar project GEN-2022-109, Lea County
Solar
150 MWWithdrawn / abandoned Lea, NMSPP Jan 2023target 2026
Solar project GEN-2024-011, Lea County
Solar
150 MWWithdrawn / abandoned Lea, NMSPP Dec 2023target 2026
Onshore wind project GEN-2023-096, Quay County
Onshore wind
150 MWWithdrawn / abandoned Quay, NMSPP Oct 2023target 2028
Solar project GEN-2024-010, Lea County
Solar
150 MWWithdrawn / abandoned Lea, NMSPP Dec 2023target 2026
Solar project GEN-2024-008, Lea County
Solar
150 MWWithdrawn / abandoned Lea, NMSPP Dec 2023target 2026
Battery storage project GEN-2022-135, Lea County
Battery storage
150 MWWithdrawn / abandoned Lea, NMSPP Feb 2023target 2027
Battery storage project GEN-2022-128, Eddy County
Battery storage
150 MWWithdrawn / abandoned Eddy, NMSPP Feb 2023target 2027
Solar + storage project IA-PNM-2023-31, Mckinley County
Solar + storage
100 MWWithdrawn / abandoned Mckinley, NMWest Sep 2023target 2028
Solar + storage project IA-PNM-2023-13, Valencia County
Solar + storage
100 MWWithdrawn / abandoned Valencia, NMWest Jan 2023target 2026
Battery storage project IA-PNM-2023-23, Torrance County
Battery storage
100 MWWithdrawn / abandoned Torrance, NMWest Sep 2023target 2028
Battery storage project IA-PNM-2023-15, Roosevelt County
Battery storage
100 MWWithdrawn / abandoned Roosevelt, NMWest Sep 2023target 2028
Battery storage project IA-PNM-2023-19, Bernalillo County
Battery storage
100 MWWithdrawn / abandoned Bernalillo, NMWest Sep 2023target 2027
Solar + storage project GEN-2022-170, Curry County
Solar + storage
99.0 MWWithdrawn / abandoned Curry, NMSPP Feb 2023target 2026
Solar + storage project IA-PNM-2023-29, Cibola County
Solar + storage
80.0 MWWithdrawn / abandoned Cibola, NMWest Sep 2023target 2029
Solar project IA-PNM-2023-28, Mckinley County
Solar
80.0 MWWithdrawn / abandoned Mckinley, NMWest Sep 2023target 2028
Solar project GEN-2022-184, Curry County
Solar
59.4 MWWithdrawn / abandoned Curry, NMSPP Mar 20232024
Solar + storage project IA-PNM-2023-17, Valencia County
Solar + storage
50.0 MWWithdrawn / abandoned Valencia, NMWest Sep 2023target 2027
Solar + storage project IA-PNM-2023-32, Santa Fe County
Solar + storage
50.0 MWWithdrawn / abandoned Santa Fe, NMWest Sep 2023target 2028
Solar project GEN-2023-187, Eddy County
Solar
20.0 MWWithdrawn / abandoned Eddy, NMSPP Oct 20232023

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)