SOLAR Β· WEST

Solar project IA-PNM-2023-28, Mckinley County

Solar project IA-PNM-2023-28, Mckinley County is a 80.0 MW solar request withdrawn in the West interconnection queue, in Mckinley County, New Mexico, connecting to Public Service Company of New Mexico.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2023 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IA-PNM-2023-28
Grid region
West (non-ISO utilities)
Utility / transmission owner
Public Service Company of New Mexico
Connection point (POI)
New Substation on Ambrosia to Yah-Ta-Hey 115 kV Line
Location
Mckinley County, New Mexico
Technology
Solar: 80.0 MW
Total requested
80.0 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
29 September 2023
Proposed online date
June 2028

Location

Marker shows the centre of Mckinley County; the queue data does not give exact sites.

Power plants in New Mexico Β· Transmission lines in New Mexico

Other requests in Mckinley County