Solar project GEN-2023-001, Lea County

Solar project GEN-2023-001, Lea County is a 230 MW solar request withdrawn in the SPP interconnection queue, in Lea County, New Mexico, connecting to SPS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2023 (completed)
  2. Withdrawn / abandonedAug 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. OperatingDec 2025 (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2023-001
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
T14 Circuit 115 V Line
Location
Lea County, New Mexico
Technology
Solar: 230 MW
Total requested
230 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
26 May 2023
Proposed online date
December 2025
Came online
December 2025
Withdrawn
August 2025

Location

Marker shows the centre of Lea County; the queue data does not give exact sites.

Power plants in New Mexico Β· Transmission lines in New Mexico

Other requests in Lea County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem