πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί New Mexico

SOLAR + STORAGE Β· SPP

Solar + storage project GEN-2023-081, Lea County

Solar + storage project GEN-2023-081, Lea County is a 625 MW solar + storage request withdrawn in the SPP interconnection queue, in Lea County, New Mexico, connecting to NEET.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2023 (completed)
  2. Withdrawn / abandonedAug 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2023-081
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
NEET
Connection point (POI)
Crossroads - Hobbs 345 kV Line
Location
Lea County, New Mexico
Technology
Solar: 625 MW Β· Battery
Total requested
625 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
2 October 2023
Proposed online date
October 2028
Withdrawn
August 2025

Location

Marker shows the centre of Lea County; the queue data does not give exact sites.

Power plants in New Mexico Β· Transmission lines in New Mexico

Other requests in Lea County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem