United States β€Ί Grid β€Ί Interconnection queues β€Ί New Hampshire

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in New Hampshire (2019 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown9435 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn9435 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

9 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar
Solar
110 MWWithdrawn / abandoned Carroll, NHISO-NE Oct 2019target 2025
Energy Storage
Battery storage
100 MWWithdrawn / abandoned Grafton, NHISO-NE Mar 2019target 2023
Solar
Solar
60.0 MWWithdrawn / abandoned Grafton, NHISO-NE Jul 2019target 2022
Solar
Solar
45.0 MWWithdrawn / abandoned Coos, NHISO-NE Oct 2019target 2024
Solar
Solar
35.0 MWWithdrawn / abandoned Merrimack, NHISO-NE Nov 2019target 2022
Solar
Solar
33.1 MWWithdrawn / abandoned Grafton, NHISO-NE Jul 2019target 2022
Solar
Solar
19.8 MWWithdrawn / abandoned Sullivan, NHISO-NE Apr 2019target 2020
Pembroke Solar
Solar
17.5 MWWithdrawn / abandoned Merrimack, NHISO-NE Oct 2019target 2024
Nellie Solar
Solar
15.0 MWWithdrawn / abandoned Sullivan, NHISO-NE Apr 2019target 2024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)