United States โ€บ Grid โ€บ Interconnection queues โ€บ Nevada

OCTARY USA ยท INTERCONNECTION QUEUES

Interconnection queue in Nevada (2021 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5117.6 GW
Active in queue17.6 GW51 requests
Agreement signed8,552 MW25 requests
Withdrawn183,850 MW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

51 requests ยท page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Mosey
Solar + storage
1,081 MWAgreement signed Clark, NVCAISO Apr 2021target 2029
Water Rock Solar 2
Solar + storage
1,034 MWIn study Nye, NVCAISO Apr 2021target 2028
Silver Star Solar
Solar + storage
1,034 MWAgreement signed Nye, NVCAISO Apr 2021target 2028
Rock Valley Energy Center
Solar + storage
1,024 MWAgreement signed Nye, NVCAISO Apr 2021target 2029
Solar + storage project Company LU, Mineral County
Solar + storage
700 MWAgreement signed Mineral, NVWest Sep 2021target 2029
Solar + storage project Company MI, Churchill County
Solar + storage
700 MWAgreement signed Churchill, NVWest Sep 2021target 2024
Kawich
Solar + storage
700 MWAgreement signed Clark, NVCAISO Apr 2021target 2029
Larrea Solar
Solar + storage
614 MWIn study Clark, NVCAISO Apr 2021target 2028
Solar + storage project Company 201, Clark County
Solar + storage
600 MWPaused / redesign Clark, NVWest Sep 2021target 2029
Solar + storage project Company 200, Clark County
Solar + storage
600 MWPaused / redesign Clark, NVWest Sep 2021target 2029
Wind + storage project Company LV, White Pine County
Wind + storage
600 MWPaused / redesign White Pine, NVWest Sep 2021target 2025
Solar + storage project Company LW, Mineral County
Solar + storage
550 MWPaused / redesign Mineral, NVWest Sep 2021target 2029
Sterling
Solar + storage
500 MWIn study Clark, NVCAISO Apr 2021target 2031
Solar + storage project Company ME, Lyon County
Solar + storage
500 MWPaused / redesign Lyon, NVWest Sep 2021target 2029
Solar + storage project Company 194, Clark County
Solar + storage
400 MWAgreement signed Clark, NVWest Mar 2021target 2023
Solar + storage project Company LP, Lyon County
Solar + storage
400 MWAgreement signed Lyon, NVWest Sep 2021target 2029
Battery storage project Company 206, Clark County
Battery storage
400 MWPaused / redesign Clark, NVWest Sep 2021target 2029
Solar + storage project Company LX, Mineral County
Solar + storage
400 MWPaused / redesign Mineral, NVWest Sep 2021target 2029
Dandelion Hybrid Solar
Solar + storage
334 MWIn study Nye, NVCAISO Apr 2021target 2027
Solar + storage project Company MB, White Pine County
Solar + storage
300 MWAgreement signed White Pine, NVWest Sep 2021target 2028
Solar + storage project Company LL, Pershing County
Solar + storage
300 MWPaused / redesign Pershing, NVWest Mar 2021target 2029
Solar + storage project Company MA, White Pine County
Solar + storage
300 MWAgreement signed White Pine, NVWest Sep 2021target 2028
Solar + storage project Company MH, Churchill County
Solar + storage
300 MWAgreement signed Churchill, NVWest Sep 2021target 2024
Solar + storage project Company MJ, Lyon County
Solar + storage
300 MWPaused / redesign Lyon, NVWest Sep 2021target 2029
Solar + storage project Company 195, Clark County
Solar + storage
275 MWAgreement signed Clark, NVWest Mar 2021target 2023
Delamar Energy Storage 2
Battery storage
256 MWIn study Clark, NVCAISO Apr 2021target 2027
Geothermal project Company LM, Lyon County
Geothermal
230 MWAgreement signed Lyon, NVWest Mar 2021target 2029
Solar + storage project Company LK, Lyon County
Solar + storage
200 MWAgreement signed Lyon, NVWest Mar 2021target 2029
Solar + storage project Company 208, Clark County
Solar + storage
200 MWPaused / redesign Clark, NVWest Sep 2021target 2025
Solar + storage project Company LG, Lyon County
Solar + storage
200 MWAgreement signed Lyon, NVWest Mar 2021target 2029
Solar + storage project Company LD, Lander County
Solar + storage
200 MWPaused / redesign Lander, NVWest Mar 2021target 2029
Battery storage project Company 202, Clark County
Battery storage
200 MWPaused / redesign Clark, NVWest Sep 2021target 2024
Solar + storage project Company LZ, Eureka County
Solar + storage
200 MWPaused / redesign Eureka, NVWest Sep 2021target 2025
Solar + storage project Company MK, Lyon County
Solar + storage
200 MWPaused / redesign Lyon, NVWest Sep 2021target 2029
Battery storage project Company 197, Clark County
Battery storage
200 MWAgreement signed Clark, NVWest Mar 2021target 2024
Solar + storage project Company LC, Lander County
Solar + storage
200 MWPaused / redesign Lander, NVWest Mar 2021target 2029
Solar + storage project Company LY, Eureka County
Solar + storage
200 MWPaused / redesign Eureka, NVWest Sep 2021target 2025
Solar + storage project Company 207, Clark County
Solar + storage
200 MWPaused / redesign Clark, NVWest Sep 2021target 2025
Solar + storage project Company LE, Pershing County
Solar + storage
200 MWPaused / redesign Pershing, NVWest Mar 2021target 2029
Solar + storage project Company MG, Humboldt County
Solar + storage
170 MWAgreement signed Humboldt, NVWest Sep 2021target 2023
Geothermal project Company LB, Pershing County
Geothermal
115 MWAgreement signed Pershing, NVWest Mar 2021target 2029
Battery storage project Company 204, Clark County
Battery storage
100 MWPaused / redesign Clark, NVWest Sep 2021target 2024
Battery storage project Company 210, Clark County
Battery storage
100 MWPaused / redesign Clark, NVWest Sep 2021target 2024
Solar + storage project Company 209, Clark County
Solar + storage
100 MWPaused / redesign Clark, NVWest Sep 2021target 2029
Solar + storage project Company 193, Clark County
Solar + storage
57.0 MWAgreement signed Clark, NVWest Mar 2021target 2026
Geothermal project Company LT, Lander County
Geothermal
40.0 MWAgreement signed Lander, NVWest Sep 2021target 2026
Geothermal project Company KY, Esmeralda County
Geothermal
38.5 MWAgreement signed Esmeralda, NVWest Mar 2021target 2027
Geothermal project Company KZ, Churchill County
Geothermal
38.5 MWAgreement signed Churchill, NVWest Mar 2021target 2027
Geothermal project Company LR, Lander County
Geothermal
29.0 MWAgreement signed Lander, NVWest Sep 2021target 2024
Geothermal project Company MM, Esmeralda County
Geothermal
19.8 MWAgreement signed Esmeralda, NVWest Dec 2021target 2025
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)