In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn
| Project | Capacity | Status | Location | Region | Queued | Online |
Battery storage project GEN-2021-043, Lancaster County Battery storage |
250 MW | Agreement signed |
Lancaster, NE | SPP |
Apr 2021 | target 2030 |
Battery storage project GEN-2024-372, Douglas County Battery storage |
250 MW | In study |
Douglas, NE | SPP |
Mar 2025 | target 2028 |
Battery storage project GEN-2018-025, Washington County Battery storage |
200 MW | Paused / redesign |
Washington, NE | SPP |
May 2018 | target 2028 |
Battery storage project GEN-2024-173, Lancaster County Battery storage |
200 MW | In study |
Lancaster, NE | SPP |
Mar 2025 | target 2028 |
Battery storage project GEN-2018-033, Cass County Battery storage |
200 MW | Paused / redesign |
Cass, NE | SPP |
May 2018 | target 2029 |
Battery storage project GEN-2021-040, Cass County Battery storage |
200 MW | In study |
Cass, NE | SPP |
Apr 2021 | target 2029 |
Battery storage project GEN-2024-051, Lancaster County Battery storage |
170 MW | In study |
Lancaster, NE | SPP |
Oct 2024 | target 2028 |
Battery storage project GEN-2025-SR31, Madison County Battery storage |
170 MW | In study |
Madison, NE | SPP |
Nov 2025 | target 2026 |
Battery storage project GEN-2024-065, Dodge County Battery storage |
150 MW | In study |
Dodge, NE | SPP |
Oct 2024 | target 2029 |
Battery storage project GEN-2023-SR7, Wayne County Battery storage |
135 MW | In study |
Wayne, NE | SPP |
Dec 2022 | 2024 |
Battery storage project GEN-2021-039, Douglas County Battery storage |
100 MW | In study |
Douglas, NE | SPP |
Apr 2021 | target 2030 |
Battery storage project GEN-2018-037, Douglas County Battery storage |
100 MW | Paused / redesign |
Douglas, NE | SPP |
May 2018 | target 2030 |
Battery storage project GEN-2024-SR10, Lancaster County Battery storage |
80.0 MW | In study |
Lancaster, NE | SPP |
Apr 2024 | target 2026 |
Battery storage project GEN-2021-048, Lancaster County Battery storage |
75.0 MW | Agreement signed |
Lancaster, NE | SPP |
Apr 2021 | target 2029 |
Battery storage project GEN-2024-SR8, Greeley County Battery storage |
70.0 MW | In study |
Greeley, NE | SPP |
Apr 2024 | target 2026 |
Battery storage project GEN-2023-SR19, Jefferson County Battery storage |
50.0 MW | In study |
Jefferson, NE | SPP |
Jun 2023 | target 2026 |
Battery storage project GEN-2025-SR5, Lancaster County Battery storage |
40.0 MW | In study |
Lancaster, NE | SPP |
May 2025 | target 2026 |
Battery storage project GEN-2017-198, Douglas County Battery storage |
11.6 MW | Agreement signed |
Douglas, NE | SPP |
Nov 2017 | target 2027 |