United States › Grid › Interconnection queues › Nebraska

BATTERY STORAGE · SPP

Battery storage project GEN-2025-SR5, Lancaster County

Battery storage project GEN-2025-SR5, Lancaster County is a 40.0 MW battery storage request in interconnection study in the SPP interconnection queue, in Lancaster County, Nebraska, connecting to NPPD.

Queue statusIn planning
  1. PlanningQueued May 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Nov 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2025-SR5
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
NPPD
Connection point (POI)
Monolith 115 kV Substation
Location
Lancaster County, Nebraska
Technology
Battery: 40.0 MW
Total requested
40.0 MW
Service type
NRIS and ERIS
Study phase
FACILITY STUDY STAGE
Queue status
Active
Entered queue
22 May 2025
Proposed online date
November 2026

Location

Marker shows the centre of Lancaster County; the queue data does not give exact sites.

Power plants in Nebraska · Transmission lines in Nebraska

Other requests in Lancaster County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem