United States βΊ Grid βΊ Interconnection queues βΊ Mississippi
OCTARY USA Β· INTERCONNECTION QUEUESWithdrawn queue requests in Mississippi (2018 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Gas project J1130, Warren County Gas |
1,110 MW | Withdrawn / abandoned |
| Gas project IC-756, Lamar County Gas |
550 MW | Withdrawn / abandoned |
| Solar project J1095, Desoto County Solar |
300 MW | Withdrawn / abandoned |
| Solar project J1020, Jasper County Solar |
250 MW | Withdrawn / abandoned |
| Solar project J1049, Forrest County Solar |
250 MW | Withdrawn / abandoned |
| Solar project J988, Wayne County Solar |
200 MW | Withdrawn / abandoned |
| Solar project IC-681, Harrison County Solar |
200 MW | Withdrawn / abandoned |
| Solar project IC-707, Jasper County Solar |
160 MW | Withdrawn / abandoned |
| Solar project 344, Panola County Solar |
150 MW | Withdrawn / abandoned |
| Solar project IC-688, Perry County Solar |
125 MW | Withdrawn / abandoned |
| Solar project IC-691, Forrest County Solar |
120 MW | Withdrawn / abandoned |
| Solar project IC-682, Lamar County Solar |
120 MW | Withdrawn / abandoned |
| Solar project J1163, Quitman County Solar |
120 MW | Withdrawn / abandoned |
| Solar project J1136, Hinds County Solar |
100 MW | Withdrawn / abandoned |
| Solar project IC-683, Jones County Solar |
100 MW | Withdrawn / abandoned |
| Solar project J1070, Washington County Solar |
100 MW | Withdrawn / abandoned |
| Solar project J1157, Hinds County Solar |
100 MW | Withdrawn / abandoned |
| Solar project IC-690, Jones County Solar |
100 MW | Withdrawn / abandoned |
| Solar project J1113, Sunflower County Solar |
85.0 MW | Withdrawn / abandoned |
| Solar project IC-673, George County Solar |
79.7 MW | Withdrawn / abandoned |
| Solar project J964, Hinds County Solar |
70.0 MW | Withdrawn / abandoned |
| Solar project IC-722, Lamar County Solar |
55.0 MW | Withdrawn / abandoned |
| Solar project 343, Chickasaw County Solar |
52.0 MW | Withdrawn / abandoned |
| Solar project IC-689, Harrison County Solar |
50.0 MW | Withdrawn / abandoned |
| Solar project 348, Chickasaw County Solar |
40.0 MW | Withdrawn / abandoned |
| Solar project 349, Pontotoc County Solar |
17.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)