United States β€Ί Grid β€Ί Interconnection queues β€Ί Minnesota

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Minnesota (2022 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown315,142 MW
Active in queue5,142 MW31 requests
Agreement signed0.0 MW0 requests
Withdrawn183,583 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

31 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Replacing 710 MW of coal generation with solar at Sherco Unit 2; Sherco Unit 2
Other
710 MWIn study Sherburne, MNMISO Dec 20222024
Battery storage project J2716, Dakota County
Battery storage
300 MWIn study Dakota, MNMISO Sep 2022target 2027
Solar + storage project J3002, Pine County
Solar + storage
288 MWIn study Pine, MNMISO Sep 2022target 2025
Solar project J3021, Lyon County
Solar
235 MWIn study Lyon, MNMISO Sep 2022target 2027
Solar project J2599, Redwood County
Solar
216 MWIn study Redwood, MNMISO Sep 2022target 2026
Solar project J3039, Olmsted County
Solar
200 MWIn study Olmsted, MNMISO Sep 2022target 2029
Onshore wind project J2332, Cottonwood County
Onshore wind
200 MWIn study Cottonwood, MNMISO Sep 2022target 2027
Battery storage project J2840, Olmsted County
Battery storage
200 MWIn study Olmsted, MNMISO Sep 2022target 2025
Onshore wind project J2563, Cottonwood County
Onshore wind
200 MWIn study Cottonwood, MNMISO Sep 2022target 2026
Battery storage project J2601, Wabasha County
Battery storage
200 MWIn study Wabasha, MNMISO Sep 2022target 2026
Solar project J3041, Olmsted County
Solar
200 MWIn study Olmsted, MNMISO Sep 2022target 2029
Onshore wind project J2346, Murray County
Onshore wind
200 MWIn study Murray, MNMISO Sep 2022target 2027
Solar project J2608, Stevens County
Solar
160 MWIn study Stevens, MNMISO Sep 2022target 2026
Solar project J2561, Yellow Medicine County
Solar
153 MWIn study Yellow Medicine, MNMISO Sep 2022target 2030
Battery storage project J2731, Olmsted County
Battery storage
150 MWIn study Olmsted, MNMISO Sep 2022target 2025
Solar project J1566, Martin County
Solar
150 MWIn study Martin, MNMISO Feb 2022target 2026
Battery storage project J2730, Jackson County
Battery storage
150 MWIn study Jackson, MNMISO Sep 2022target 2025
Solar project J2749, Polk County
Solar
150 MWIn study Polk, MNMISO Sep 2022target 2026
Battery storage project J2728, Freeborn County
Battery storage
150 MWIn study Freeborn, MNMISO Sep 2022target 2025
Solar project J2501, Goodhue County
Solar
150 MWIn study Goodhue, MNMISO Sep 2022target 2024
Solar project J2861, Mower County
Solar
147 MWIn study Mower, MNMISO Sep 2022target 2029
Solar project J2885, Red Lake County
Solar
130 MWIn study Red Lake, MNMISO Sep 2022target 2025
Battery storage project J3172, Dakota County
Battery storage
100 MWIn study Dakota, MNMISO Sep 2022target 2026
Solar project J2495, Benton County
Solar
100 MWIn study Benton, MNMISO Sep 2022target 2026
Battery storage project J2879, Washington County
Battery storage
80.0 MWIn study Washington, MNMISO Sep 2022target 2025
Battery storage project J2550, Yellow Medicine County
Battery storage
75.0 MWIn study Yellow Medicine, MNMISO Sep 2022target 2030
Gas project J3213, Hennepin County
Gas
51.0 MWIn study Hennepin, MNMISO Sep 2022target 2026
Solar project J2867, Wabasha County
Solar
50.0 MWIn study Wabasha, MNMISO Sep 2022target 2029
Other project J2276, Douglas County
Other
39.5 MWIn study Douglas, MNMISO Apr 2022target 2022
Hydro project J1826, Dakota County
Hydro
4.0 MWIn study Dakota, MNMISO Sep 2022target 2024
Hydro project J3219, Dakota County
Hydro
3.0 MWIn study Dakota, MNMISO Sep 2022target 2023

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)