Withdrawn queue requests in Minnesota (2021 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown172,300 MW
Active in queue832 MW5 requests
Agreement signed0.0 MW0 requests
Withdrawn172,300 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

17 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Replace 350 MW of ALTW.FPL_DAEC Unit with Solar; Duane Arnold
Other
350 MWWithdrawn / abandoned Otter Tail, MNMISO Feb 2021target 2023
Solar project J2065, Pipestone County
Solar
200 MWWithdrawn / abandoned Pipestone, MNMISO Jul 2021target 2024
Solar project J2037, Olmsted County
Solar
200 MWWithdrawn / abandoned Olmsted, MNMISO Jul 2021target 2024
Battery storage project J2200, Scott County
Battery storage
200 MWWithdrawn / abandoned Scott, MNMISO Aug 2021target 2024
Solar project J1847, Mower County
Solar
200 MWWithdrawn / abandoned Mower, MNMISO Aug 2021target 2024
Solar project J2022, Mower County
Solar
200 MWWithdrawn / abandoned Mower, MNMISO Oct 2021target 2024
Battery storage project J2199, Anoka County
Battery storage
200 MWWithdrawn / abandoned Anoka, MNMISO Aug 2021target 2024
Solar project J2291, Polk County
Solar
150 MWWithdrawn / abandoned Polk, MNMISO Sep 2021target 2025
Solar project J2030, Isanti County
Solar
120 MWWithdrawn / abandoned Isanti, MNMISO Jul 2021target 2024
Onshore wind project J2092, Wright County
Onshore wind
100 MWWithdrawn / abandoned Wright, MNMISO Aug 2021target 2025
Solar project J2286, Polk County
Solar
90.0 MWWithdrawn / abandoned Polk, MNMISO Jul 2021target 2026
Onshore wind project J2054, Freeborn County
Onshore wind
67.0 MWWithdrawn / abandoned Freeborn, MNMISO Aug 2021target 2024
Solar project J1941, Polk County
Solar
60.0 MWWithdrawn / abandoned Polk, MNMISO Aug 2021target 2026
Replace 49 MW of GRE.ELKRI1 Unit with Gas/Oil; Elk River 1
Gas
49.0 MWWithdrawn / abandoned Sherburne, MNMISO Jan 2021target 2022
Battery storage project J2285, Polk County
Battery storage
45.0 MWWithdrawn / abandoned Polk, MNMISO Jul 2021target 2026
Onshore wind project J2067, Clay County
Onshore wind
39.4 MWWithdrawn / abandoned Clay, MNMISO Sep 2021target 2024
Battery storage project J1968, Polk County
Battery storage
30.0 MWWithdrawn / abandoned Polk, MNMISO Aug 2021target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)