Withdrawn queue requests in Minnesota (2016 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown263,748 MW
Active in queue155 MW3 requests
Agreement signed105 MW2 requests
Withdrawn263,748 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

26 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project J671, Martin County
Onshore wind
400 MWWithdrawn / abandoned Martin, MNMISO Jul 2016target 2019
Onshore wind project J627, Meeker County
Onshore wind
400 MWWithdrawn / abandoned Meeker, MNMISO May 2016target 2019
Onshore wind project J626, Meeker County
Onshore wind
400 MWWithdrawn / abandoned Meeker, MNMISO May 2016target 2019
Onshore wind project J594, Jackson County
Onshore wind
300 MWWithdrawn / abandoned Jackson, MNMISO May 2016target 2018
Onshore wind project J742, Cottonwood County
Onshore wind
211 MWWithdrawn / abandoned Cottonwood, MNMISO Nov 2016target 2020
Onshore wind project J739, Lyon County
Onshore wind
200 MWWithdrawn / abandoned Lyon, MNMISO Nov 2016target 2020
Onshore wind project J761, Faribault County
Onshore wind
200 MWWithdrawn / abandoned Faribault, MNMISO Nov 2016target 2020
Onshore wind project J781, Kandiyohi County
Onshore wind
170 MWWithdrawn / abandoned Kandiyohi, MNMISO Nov 2016target 2018
Onshore wind project J612, Kittson County
Onshore wind
150 MWWithdrawn / abandoned Kittson, MNMISO May 2016target 2018
Solar project J548, Yellow Medicine County
Solar
150 MWWithdrawn / abandoned Yellow Medicine, MNMISO Mar 2016target 2018
Onshore wind project J556, Renville County
Onshore wind
102 MWWithdrawn / abandoned Renville, MNMISO Apr 2016target 2019
Onshore wind project J596, Big Stone County
Onshore wind
100 MWWithdrawn / abandoned Big Stone, MNMISO May 2016target 2018
Solar project J702, Wadena County
Solar
100 MWWithdrawn / abandoned Wadena, MNMISO Sep 2016target 2018
Onshore wind project J575, Lincoln County
Onshore wind
100 MWWithdrawn / abandoned Lincoln, MNMISO May 2016target 2018
Onshore wind project J745, Nobles County
Onshore wind
100 MWWithdrawn / abandoned Nobles, MNMISO Nov 2016target 2021
Solar project J735, Morrison County
Solar
100 MWWithdrawn / abandoned Morrison, MNMISO Nov 2016target 2019
Onshore wind project J577, Pipestone County
Onshore wind
100 MWWithdrawn / abandoned Pipestone, MNMISO May 2016target 2018
Solar project J547, Sherburne County
Solar
100 MWWithdrawn / abandoned Sherburne, MNMISO Mar 2016target 2018
Solar project J770, Renville County
Solar
90.0 MWWithdrawn / abandoned Renville, MNMISO Nov 2016target 2019
Solar project J624, Yellow Medicine County
Solar
80.0 MWWithdrawn / abandoned Yellow Medicine, MNMISO May 2016target 2018
Solar project J771, Stearns County
Solar
50.0 MWWithdrawn / abandoned Stearns, MNMISO Nov 2016target 2019
Onshore wind project J574, Kandiyohi County
Onshore wind
40.0 MWWithdrawn / abandoned Kandiyohi, MNMISO May 2016target 2017
Solar project J784, Renville County
Solar
40.0 MWWithdrawn / abandoned Renville, MNMISO Nov 2016target 2018
Solar project J769, Renville County
Solar
33.0 MWWithdrawn / abandoned Renville, MNMISO Nov 2016target 2019
Solar project J623, Yellow Medicine County
Solar
20.0 MWWithdrawn / abandoned Yellow Medicine, MNMISO May 2016target 2018
Solar project MPC03000, Beltrami County
Solar
12.0 MWWithdrawn / abandoned Beltrami, MNMISO Sep 2016target 2017

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)