SOLAR Β· MISO

Solar project J771, Stearns County

Solar project J771, Stearns County is a 50.0 MW solar request withdrawn in the MISO interconnection queue, in Stearns County, Minnesota, connecting to GREAT RIVER ENERGY.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2016 (completed)
  2. Withdrawn / abandonedApr 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J771
Grid region
MISO (Midcontinent)
Utility / transmission owner
GREAT RIVER ENERGY
Connection point (POI)
Lake Koronis-Paynesville 69kV
Location
Stearns County, Minnesota
Technology
Solar: 50.0 MW
Total requested
50.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
14 November 2016
Proposed online date
July 2019
Withdrawn
April 2019

Location

Marker shows the centre of Stearns County; the queue data does not give exact sites.