Battery storage project J2590, Huron County Battery storage |
500 MW | In study |
Huron, MI | MISO |
Sep 2022 | target 2025 |
Battery storage project J2628, Huron County Battery storage |
250 MW | In study |
Huron, MI | MISO |
Sep 2022 | target 2028 |
Solar project J2921, Calhoun County Solar |
250 MW | In study |
Calhoun, MI | MISO |
Sep 2022 | target 2026 |
Battery storage project J2567, Oceana County Battery storage |
240 MW | In study |
Oceana, MI | MISO |
Sep 2022 | target 2025 |
Solar project J2673, Clare County Solar |
225 MW | In study |
Clare, MI | MISO |
Sep 2022 | target 2025 |
Solar project J2668, Mason County Solar |
225 MW | In study |
Mason, MI | MISO |
Sep 2022 | target 2025 |
Solar project J2670, Mason County Solar |
223 MW | In study |
Mason, MI | MISO |
Sep 2022 | target 2025 |
Solar project J2444, Van Buren County Solar |
220 MW | In study |
Van Buren, MI | MISO |
Sep 2022 | target 2026 |
Solar project J2814, Kalamazoo County Solar |
220 MW | In study |
Kalamazoo, MI | MISO |
Sep 2022 | target 2026 |
Solar project J2611, Alcona County Solar |
215 MW | In study |
Alcona, MI | MISO |
Sep 2022 | target 2028 |
Solar project J2878, Sanilac County Solar |
200 MW | In study |
Sanilac, MI | MISO |
Sep 2022 | target 2025 |
Battery storage project J2991, Wayne County Battery storage |
200 MW | In study |
Wayne, MI | MISO |
Sep 2022 | target 2025 |
Solar project J2672, Shiawassee County Solar |
200 MW | In study |
Shiawassee, MI | MISO |
Sep 2022 | target 2025 |
Solar project J2877, Midland County Solar |
200 MW | In study |
Midland, MI | MISO |
Sep 2022 | target 2025 |
Battery storage project J2889, Allegan County Battery storage |
200 MW | In study |
Allegan, MI | MISO |
Sep 2022 | target 2025 |
Battery storage project J2906, Kalamazoo County Battery storage |
200 MW | In study |
Kalamazoo, MI | MISO |
Sep 2022 | target 2024 |
Solar project J2485, Livingston County Solar |
200 MW | In study |
Livingston, MI | MISO |
Sep 2022 | target 2025 |
Solar project J2374, Sanilac County Solar |
200 MW | In study |
Sanilac, MI | MISO |
Sep 2022 | target 2025 |
Battery storage project J2475, Monroe County Battery storage |
200 MW | In study |
Monroe, MI | MISO |
Sep 2022 | target 2026 |
Solar project J2667, Sanilac County Solar |
200 MW | In study |
Sanilac, MI | MISO |
Sep 2022 | target 2025 |
Solar project J2676, Huron County Solar |
200 MW | In study |
Huron, MI | MISO |
Sep 2022 | target 2025 |
Solar project J2486, Monroe County Solar |
200 MW | In study |
Monroe, MI | MISO |
Sep 2022 | target 2025 |
Battery storage project J2822, Van Buren County Battery storage |
200 MW | In study |
Van Buren, MI | MISO |
Sep 2022 | target 2025 |
Battery storage project J2684, St. Clair County Battery storage |
200 MW | In study |
St. Clair, MI | MISO |
Sep 2022 | target 2025 |
Solar project J2677, St. Clair County Solar |
200 MW | In study |
St. Clair, MI | MISO |
Sep 2022 | target 2025 |
Solar + storage project AH2-373, Berrien County Solar + storage |
180 MW | In study |
Berrien, MI | PJM |
Mar 2022 | target 2028 |
Solar project J2578, Tuscola County Solar |
180 MW | In study |
Tuscola, MI | MISO |
Sep 2022 | target 2026 |
Solar project J3059, Midland County Solar |
175 MW | In study |
Midland, MI | MISO |
Sep 2022 | target 2026 |
Solar project J2876, Arenac County Solar |
175 MW | In study |
Arenac, MI | MISO |
Sep 2022 | target 2025 |
Solar project J2675, Gladwin County Solar |
170 MW | In study |
Gladwin, MI | MISO |
Sep 2022 | target 2025 |
Solar + storage project J2786, Allegan County Solar + storage |
170 MW | In study |
Allegan, MI | MISO |
Sep 2022 | target 2024 |
Battery storage project J2997, Livingston County Battery storage |
160 MW | In study |
Livingston, MI | MISO |
Sep 2022 | target 2025 |
Battery storage project J2378, Macomb County Battery storage |
152 MW | In study |
Macomb, MI | MISO |
Sep 2022 | target 2026 |
Solar project J2678, Delta County Solar |
150 MW | In study |
Delta, MI | MISO |
Sep 2022 | target 2025 |
Solar project J2875, Presque Isle County Solar |
150 MW | In study |
Presque Isle, MI | MISO |
Sep 2022 | target 2025 |
Battery storage project AI1-166, Cass County Battery storage |
150 MW | In study |
Cass, MI | PJM |
Sep 2022 | target 2028 |
Solar + storage project AH2-149, Van Buren County Solar + storage |
150 MW | In study |
Van Buren, MI | PJM |
Feb 2022 | target 2026 |
Solar project J3134, Otsego County Solar |
150 MW | In study |
Otsego, MI | MISO |
Sep 2022 | target 2025 |
Battery storage project J3009, Washtenaw County Battery storage |
150 MW | In study |
Washtenaw, MI | MISO |
Aug 2022 | target 2025 |
Battery storage project J2454, Montcalm County Battery storage |
150 MW | In study |
Montcalm, MI | MISO |
Sep 2022 | target 2025 |
Battery storage project J2589, Jackson County Battery storage |
150 MW | In study |
Jackson, MI | MISO |
Sep 2022 | target 2025 |
Solar project J1750, Marquette County Solar |
150 MW | Under construction |
Marquette, MI | MISO |
Apr 2022 | target 2026 |
Solar project J2669, Mason County Solar |
140 MW | In study |
Mason, MI | MISO |
Sep 2022 | target 2025 |
Solar project J2815, Calhoun County Solar |
140 MW | In study |
Calhoun, MI | MISO |
Aug 2022 | target 2026 |
Solar + storage project J2619, Montcalm County Solar + storage |
140 MW | In study |
Montcalm, MI | MISO |
Sep 2022 | target 2026 |
Solar project J2812, Hillsdale County Solar |
140 MW | In study |
Hillsdale, MI | MISO |
Sep 2022 | target 2026 |
Solar project J2490, Tuscola County Solar |
125 MW | In study |
Tuscola, MI | MISO |
Sep 2022 | target 2025 |
Solar project J3124, Saginaw County Solar |
120 MW | In study |
Saginaw, MI | MISO |
Sep 2022 | target 2026 |
Battery storage project J2588, Jackson County Battery storage |
120 MW | In study |
Jackson, MI | MISO |
Sep 2022 | target 2025 |
Battery storage project J3133, Saginaw County Battery storage |
120 MW | In study |
Saginaw, MI | MISO |
Sep 2022 | target 2026 |