Interconnection queue in Michigan (2021 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown304,424 MW
Active in queue4,424 MW30 requests
Agreement signed550 MW3 requests
Withdrawn415,946 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

30 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J2098, Calhoun County
Solar
309 MWIn study Calhoun, MIMISO Aug 2021target 2026
Onshore wind project J2260, Presque Isle County
Onshore wind
252 MWIn study Presque Isle, MIMISO Oct 2021target 2023
Solar + storage project J2139, Livingston County
Solar + storage
250 MWIn study Livingston, MIMISO Sep 2021target 2024
Battery storage project J2100, Van Buren County
Battery storage
250 MWIn study Van Buren, MIMISO Aug 2021target 2024
Solar project J2001, Newaygo County
Solar
220 MWIn study Newaygo, MIMISO Aug 2021target 2025
Solar project J1571, Lenawee County
Solar
200 MWAgreement signed Lenawee, MIMISO Dec 2021target 2025
Solar project J2061, Saginaw County
Solar
200 MWIn study Saginaw, MIMISO Aug 2021target 2024
Solar project J1603, Otsego County
Solar
200 MWAgreement signed Otsego, MIMISO Dec 2021target 2025
Battery storage project J1902, Wayne County
Battery storage
200 MWIn study Wayne, MIMISO Aug 2021target 2024
Battery storage project J1894, Kalamazoo County
Battery storage
200 MWIn study Kalamazoo, MIMISO Oct 2021target 2024
Solar project J1663, Ottawa County
Solar
200 MWUnder construction Ottawa, MIMISO Dec 2021target 2025
Battery storage project J1900, Wayne County
Battery storage
200 MWIn study Wayne, MIMISO Aug 2021target 2024
Solar project J1944, Sanilac County
Solar
185 MWIn study Sanilac, MIMISO Aug 2021target 2023
Solar project J1917, Livingston County
Solar
165 MWIn study Livingston, MIMISO Aug 2021target 2023
Solar project J1553, Clinton County
Solar
150 MWAgreement signed Clinton, MIMISO Dec 2021target 2025
Solar + storage project J2129, Barry County
Solar + storage
150 MWIn study Barry, MIMISO Aug 2021target 2024
Solar project J1918, Montcalm County
Solar
132 MWIn study Montcalm, MIMISO Aug 2021target 2026
Solar project J1929, Cheboygan County
Solar
110 MWIn study Cheboygan, MIMISO Aug 2021target 2025
Battery storage project J2064, Jackson County
Battery storage
100 MWIn study Jackson, MIMISO Nov 2021target 2024
Battery storage project J2026, Gratiot County
Battery storage
100 MWIn study Gratiot, MIMISO Nov 2021target 2022
Solar + storage project J2057, Montcalm County
Solar + storage
100 MWIn study Montcalm, MIMISO Aug 2021target 2024
Solar project J1932, Gladwin County
Solar
100 MWIn study Gladwin, MIMISO Aug 2021target 2024
Solar + storage project J2069, Montcalm County
Solar + storage
100 MWIn study Montcalm, MIMISO Nov 2021target 2027
Solar project J2316, Dickinson County
Solar
77.5 MWIn study Dickinson, MIMISO Sep 2021target 2023
Solar project J2029, Marquette County
Solar
62.5 MWIn study Marquette, MIMISO Nov 2021target 2024
Battery storage project J1863, Otsego County
Battery storage
60.0 MWIn study Otsego, MIMISO Aug 2021target 2024
Battery storage project J1880, Ottawa County
Battery storage
60.0 MWIn study Ottawa, MIMISO Aug 2021target 2024
Battery storage project J1984, Ottawa County
Battery storage
50.0 MWIn study Ottawa, MIMISO Aug 2021target 2024
Battery storage project J1982, Gladwin County
Battery storage
25.0 MWIn study Gladwin, MIMISO Nov 2021target 2024
Onshore wind project J2283, Hillsdale County
Onshore wind
16.1 MWIn study Hillsdale, MIMISO Nov 2021target 2020

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)