Projects with signed interconnection agreements in Michigan

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown374,949 MW
Active in queue58.6 GW305 requests
Agreement signed4,949 MW37 requests
Withdrawn39070.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

37 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project J1586, Calhoun County
Solar + storage
499 MWAgreement signed Calhoun, MIMISO Jun 2020target 2025
Onshore wind project J1557, Sanilac County
Onshore wind
293 MWAgreement signed Sanilac, MIMISO Jun 2020target 2026
Solar project J1614, Muskegon County
Solar
250 MWAgreement signed Muskegon, MIMISO Jun 2020target 2025
Solar project J1571, Lenawee County
Solar
200 MWAgreement signed Lenawee, MIMISO Dec 2021target 2025
Solar project J1525, Huron County
Solar
200 MWAgreement signed Huron, MIMISO Jun 2020target 2026
Solar project J1603, Otsego County
Solar
200 MWAgreement signed Otsego, MIMISO Dec 2021target 2025
Solar project J1196, Sanilac County
Solar
200 MWAgreement signed Sanilac, MIMISO Apr 2019target 2025
Solar project J1664, St. Clair County
Solar
200 MWAgreement signed St. Clair, MIMISO Jun 2020target 2026
Solar project J1379, Montcalm County
Solar
200 MWAgreement signed Montcalm, MIMISO Apr 2019target 2025
Solar project J1550, Branch County
Solar
200 MWAgreement signed Branch, MIMISO Jun 2020target 2025
Solar project J1062, Washtenaw County
Solar
200 MWAgreement signed Washtenaw, MIMISO Mar 2018target 2023
Onshore wind project J1292, Ionia County
Onshore wind
198 MWAgreement signed Ionia, MIMISO Apr 2019target 2024
Solar project J1658, Hillsdale County
Solar
180 MWAgreement signed Hillsdale, MIMISO May 2025target 2025
Solar project J1553, Clinton County
Solar
150 MWAgreement signed Clinton, MIMISO Dec 2021target 2025
Gemstone Solar
Solar
150 MWAgreement signed Cass, MIPJM Jan 2020target 2028
Solar project J1320, Branch County
Solar
150 MWAgreement signed Branch, MIMISO Apr 2019target 2025
Solar project J1389, Saginaw County
Solar
120 MWAgreement signed Saginaw, MIMISO Apr 2019target 2025
Solar project J1248, Calhoun County
Solar
100 MWAgreement signed Calhoun, MIMISO Apr 2019target 2025
Solar project J1430, Calhoun County
Solar
100 MWAgreement signed Calhoun, MIMISO Apr 20192023
Solar project J1331, St. Clair County
Solar
100 MWAgreement signed St. Clair, MIMISO Apr 2019target 2025
Surplus; Polaris Solar
Other
100 MWAgreement signed Gratiot, MIMISO Apr 2022target 2023
Solar project J1587, Muskegon County
Solar
100 MWAgreement signed Muskegon, MIMISO Jun 2020target 2025
Solar project J1472, Jackson County
Solar
100 MWAgreement signed Jackson, MIMISO Apr 2019target 2024
Southwest Michigan Energy Center
Solar
100 MWAgreement signed Van Buren, MIPJM Dec 2017target 2027
Battery storage project J1635, Branch County
Battery storage
100 MWAgreement signed Branch, MIMISO Jun 2020target 2025
Solar project J1399, Ingham County
Solar
90.0 MWAgreement signed Ingham, MIMISO Apr 2019target 2025
Murch Solar
Solar
85.0 MWAgreement signed Van Buren, MIPJM Aug 2019target 2027
Surplus; Pine River Solar
Other
80.0 MWAgreement signed Gratiot, MIMISO Apr 2022target 2023
Battery storage project J230, Mason County
Battery storage
70.0 MWAgreement signed Mason, MIMISO Sep 20112019
Decatur Battery Storage
Battery storage Β· Decatur Storage LLC
50.0 MWAgreement signed Van Buren, MIPJM Sep 2019target 2029
Solar project J1210, Iosco County
Solar
50.0 MWAgreement signed Iosco, MIMISO Apr 2019target 2025
Battery storage project J466, Huron County
Battery storage
30.0 MWAgreement signed Huron, MIMISO May 2015target 2015
Gas project J1798, Wayne County
Gas
25.0 MWAgreement signed Wayne, MIMISO Jun 2020target 2023
Decatur Battery Storage
Battery storage Β· Decatur Storage LLC
25.0 MWAgreement signed Van Buren, MIPJM Aug 2020target 2029
Gas project J1262, Wayne County
Gas
25.0 MWAgreement signed Wayne, MIMISO Apr 2019target 2022
Solar project J1814, Dickinson County
Solar
22.5 MWAgreement signed Dickinson, MIMISO Jun 2020target 2026
Gas project J571, Kalamazoo County
Gas
6.4 MWAgreement signed Kalamazoo, MIMISO May 2016target 2018

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)