United States โ€บ Grid โ€บ Interconnection queues โ€บ Louisiana

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in Louisiana (2024 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown4510.2 GW
Active in queue3,598 MW14 requests
Agreement signed0.0 MW0 requests
Withdrawn4510.2 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

45 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project J3796, Calcasieu Parish County
Gas
770 MWWithdrawn / abandoned Calcasieu Parish, LAMISO Apr 2024target 2028
Gas project J3871, St. Charles Parish County
Gas
770 MWWithdrawn / abandoned St. Charles Parish, LAMISO Dec 2024target 2028
Gas project J3842, Richland Parish County
Gas
770 MWWithdrawn / abandoned Richland Parish, LAMISO Oct 2024target 2028
Gas project J3841, Richland Parish County
Gas
770 MWWithdrawn / abandoned Richland Parish, LAMISO Oct 2024target 2028
Solar project J3513, Acadia Parish County
Solar
550 MWWithdrawn / abandoned Acadia Parish, LAMISO Apr 2024target 2028
Onshore wind project J3273, Madison Parish County
Onshore wind
474 MWWithdrawn / abandoned Madison Parish, LAMISO Apr 2024target 2027
Solar project J3408, Sabine Parish County
Solar
450 MWWithdrawn / abandoned Sabine Parish, LAMISO Apr 2024target 2028
Solar project J3760, Richland Parish County
Solar
405 MWWithdrawn / abandoned Richland Parish, LAMISO Apr 2024target 2028
Battery storage project J3311, St. Landry Parish County
Battery storage
400 MWWithdrawn / abandoned St. Landry Parish, LAMISO Apr 2024target 2027
Solar project J3322, Jefferson Davis Parish County
Solar
325 MWWithdrawn / abandoned Jefferson Davis Parish, LAMISO Apr 2024target 2028
Solar + storage project J3746, Grant Parish County
Solar + storage
250 MWWithdrawn / abandoned Grant Parish, LAMISO Apr 2024target 2028
Solar project J3295, Beauregard Parish County
Solar
250 MWWithdrawn / abandoned Beauregard Parish, LAMISO Apr 2024target 2027
Solar project J3572, Catahoula Parish County
Solar
200 MWWithdrawn / abandoned Catahoula Parish, LAMISO Apr 2024target 2028
Solar project J3573, Morehouse Parish County
Solar
200 MWWithdrawn / abandoned Morehouse Parish, LAMISO Apr 2024target 2028
Battery storage project J3581, Avoyelles Parish County
Battery storage
200 MWWithdrawn / abandoned Avoyelles Parish, LAMISO Apr 2024target 2028
Battery storage project J3771, Sabine Parish County
Battery storage
200 MWWithdrawn / abandoned Sabine Parish, LAMISO Apr 2024target 2028
Solar project J3612, Sabine Parish County
Solar
200 MWWithdrawn / abandoned Sabine Parish, LAMISO Apr 2024target 2028
Solar project J3603, Morehouse Parish County
Solar
175 MWWithdrawn / abandoned Morehouse Parish, LAMISO Apr 2024target 2028
Surplus; J1669
Other
165 MWWithdrawn / abandoned Jefferson Davis Parish, LAMISO Apr 2024target 2026
Solar project J3238, Evangeline Parish County
Solar
155 MWWithdrawn / abandoned Evangeline Parish, LAMISO Apr 2024target 2028
Solar project J3663, Morehouse Parish County
Solar
150 MWWithdrawn / abandoned Morehouse Parish, LAMISO Apr 2024target 2028
Battery storage project J3585, Sabine Parish County
Battery storage
150 MWWithdrawn / abandoned Sabine Parish, LAMISO Apr 2024target 2028
Solar project J3377, Madison Parish County
Solar
150 MWWithdrawn / abandoned Madison Parish, LAMISO Apr 2024target 2028
Solar + storage project J3319, Webster Parish County
Solar + storage
150 MWWithdrawn / abandoned Webster Parish, LAMISO Apr 2024target 2028
Onshore wind project J3363, Tensas Parish County
Onshore wind
150 MWWithdrawn / abandoned Tensas Parish, LAMISO Apr 2024target 2028
Solar + storage project J3582, Beauregard Parish County
Solar + storage
150 MWWithdrawn / abandoned Beauregard Parish, LAMISO Apr 2024target 2028
Solar project J3378, Jackson Parish County
Solar
140 MWWithdrawn / abandoned Jackson Parish, LAMISO Apr 2024target 2028
Solar project J3822, Pointe Coupee Parish County
Solar
140 MWWithdrawn / abandoned Pointe Coupee Parish, LAMISO Apr 2024target 2028
Solar + storage project J3534, Madison Parish County
Solar + storage
125 MWWithdrawn / abandoned Madison Parish, LAMISO Apr 2024target 2028
Solar project J3365, Tangipahoa Parish County
Solar
100 MWWithdrawn / abandoned Tangipahoa Parish, LAMISO Mar 2024target 2028
Solar project J3406, Calcasieu Parish County
Solar
100 MWWithdrawn / abandoned Calcasieu Parish, LAMISO Apr 2024target 2028
Solar project J3793, Rapides Parish County
Solar
100 MWWithdrawn / abandoned Rapides Parish, LAMISO Apr 2024target 2028
Solar project J3594, Jefferson Davis Parish County
Solar
100 MWWithdrawn / abandoned Jefferson Davis Parish, LAMISO Apr 2024target 2026
Solar + storage project J3609, Beauregard Parish County
Solar + storage
93.1 MWWithdrawn / abandoned Beauregard Parish, LAMISO Apr 2024target 2027
Solar + storage project J3659, Avoyelles Parish County
Solar + storage
90.3 MWWithdrawn / abandoned Avoyelles Parish, LAMISO Apr 2024target 2027
Solar project J3367, Avoyelles Parish County
Solar
88.0 MWWithdrawn / abandoned Avoyelles Parish, LAMISO Apr 2024target 2028
Solar project J3272, Concordia Parish County
Solar
85.0 MWWithdrawn / abandoned Concordia Parish, LAMISO Apr 2024target 2028
Solar + storage project J3625, Winn Parish County
Solar + storage
82.0 MWWithdrawn / abandoned Winn Parish, LAMISO Apr 2024target 2027
Solar project J3738, Vermilion Parish County
Solar
65.0 MWWithdrawn / abandoned Vermilion Parish, LAMISO Apr 2024target 2026
Solar project J3631, Vermilion Parish County
Solar
60.0 MWWithdrawn / abandoned Vermilion Parish, LAMISO Apr 2024target 2027
Solar project J3364, St. Martin Parish County
Solar
50.0 MWWithdrawn / abandoned St. Martin Parish, LAMISO Apr 2024target 2027
Battery storage project J3452, Morehouse Parish County
Battery storage
50.0 MWWithdrawn / abandoned Morehouse Parish, LAMISO Apr 2024target 2028
Solar + storage project J3839, Union Parish County
Solar + storage
50.0 MWWithdrawn / abandoned Union Parish, LAMISO May 2024target 2028
Battery storage project J3600, Morehouse Parish County
Battery storage
50.0 MWWithdrawn / abandoned Morehouse Parish, LAMISO Apr 2024target 2028
Other project J3765, St. James Parish County
Other
8.0 MWWithdrawn / abandoned St. James Parish, LAMISO Apr 2024target 2024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)