United States βΊ Grid βΊ Interconnection queues βΊ Louisiana
SOLAR Β· MISOSolar project J3631, Vermilion Parish County
Solar project J3631, Vermilion Parish County is a 60.0 MW solar request withdrawn in the MISO interconnection queue, in Vermilion Parish County, Louisiana, connecting to ENTERGY LOUISIANA.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2024 (completed)
- Withdrawn / abandonedOct 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J3631
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ENTERGY LOUISIANA
- Connection point (POI)
- GUEYDAN TAP - MORSE 69.0kV
- Location
- Vermilion Parish County, Louisiana
- Technology
- Solar: 60.0 MW
- Total requested
- 60.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 1
- Queue status
- Withdrawn
- Entered queue
- 18 April 2024
- Proposed online date
- December 2027
- Withdrawn
- October 2025
Location
Marker shows the centre of Vermilion Parish County; the queue data does not give exact sites.
Power plants in Louisiana Β· Transmission lines in Louisiana
Other requests in Vermilion Parish County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem