Battery storage project GEN-2020-057, Finney County Battery storage |
425 MW | Agreement signed |
Finney, KS | SPP |
Apr 2020 | target 2030 |
Battery storage project GEN-2021-005, Saline County Battery storage |
350 MW | Agreement signed |
Saline, KS | SPP |
May 2021 | target 2030 |
Battery storage project GEN-2024-339, Leavenworth County Battery storage |
300 MW | In study |
Leavenworth, KS | SPP |
Mar 2025 | target 2029 |
Battery storage project GEN-2025-SR16, Sumner County Battery storage |
300 MW | In study |
Sumner, KS | SPP |
Jun 2025 | target 2026 |
Battery storage project GEN-2021-006, Labette County Battery storage |
300 MW | In study |
Labette, KS | SPP |
May 2021 | target 2026 |
Battery storage project GEN-2021-029, Linn County Battery storage |
254 MW | In study |
Linn, KS | SPP |
May 2021 | target 2026 |
Battery storage project GEN-2024-176, Reno County Battery storage |
250 MW | In study |
Reno, KS | SPP |
Mar 2025 | target 2028 |
Battery storage project GEN-2024-330, Butler County Battery storage |
225 MW | In study |
Butler, KS | SPP |
Mar 2025 | target 2028 |
Battery storage project GEN-2020-090, Bourbon County Battery storage |
204 MW | In study |
Bourbon, KS | SPP |
Apr 2020 | target 2026 |
Battery storage project GEN-2017-227, Sedgwick County Battery storage |
202 MW | Agreement signed |
Sedgwick, KS | SPP |
Nov 2017 | target 2030 |
Battery storage project GEN-2023-037, Wyandotte County Battery storage |
200 MW | In study |
Wyandotte, KS | SPP |
Oct 2023 | target 2028 |
Battery storage project GEN-2024-061, Cowley County Battery storage |
200 MW | In study |
Cowley, KS | SPP |
Oct 2024 | target 2028 |
Battery storage project GEN-2022-024, Bourbon County Battery storage |
200 MW | In study |
Bourbon, KS | SPP |
Jun 2022 | target 2028 |
Battery storage project GEN-2024-189, Ford County Battery storage |
199 MW | In study |
Ford, KS | SPP |
Mar 2025 | target 2028 |
Battery storage project GEN-2024-320, Wyandotte County Battery storage |
199 MW | In study |
Wyandotte, KS | SPP |
Mar 2025 | target 2028 |
Battery storage project GEN-2024-319, Wyandotte County Battery storage |
199 MW | In study |
Wyandotte, KS | SPP |
Mar 2025 | target 2028 |
Battery storage project GEN-2024-121, Leavenworth County Battery storage |
199 MW | In study |
Leavenworth, KS | SPP |
Mar 2025 | target 2028 |
Battery storage project ERAS-2025-029, Wyandotte County Battery storage |
170 MW | In study |
Wyandotte, KS | SPP |
Oct 2025 | target 2027 |
Battery storage project GEN-2017-221, Sedgwick County Battery storage |
152 MW | Agreement signed |
Sedgwick, KS | SPP |
Nov 2017 | target 2026 |
Battery storage project GEN-2024-276, Shawnee County Battery storage |
150 MW | In study |
Shawnee, KS | SPP |
Mar 2025 | target 2030 |
Battery storage project GEN-2021-103, Johnson County Battery storage |
150 MW | Agreement signed |
Johnson, KS | SPP |
May 2021 | target 2030 |
Battery storage project GEN-2025-SR4, Edwards County Battery storage |
150 MW | In study |
Edwards, KS | SPP |
Aug 2025 | target 2028 |
Battery storage project GEN-2025-SR3, Clark County Battery storage |
150 MW | In study |
Clark, KS | SPP |
Aug 2025 | target 2028 |
Battery storage project GEN-2024-277, Shawnee County Battery storage |
150 MW | In study |
Shawnee, KS | SPP |
Mar 2025 | target 2030 |
Battery storage project GEN-2017-196, Johnson County Battery storage |
128 MW | Agreement signed |
Johnson, KS | SPP |
Nov 2017 | target 2030 |
Battery storage project GEN-2018-108, Barber County Battery storage |
95.0 MW | Agreement signed |
Barber, KS | SPP |
Nov 2018 | target 2028 |
Battery storage project GEN-2024-322, Graham County Battery storage |
75.0 MW | In study |
Graham, KS | SPP |
Mar 2025 | target 2029 |
Battery storage project GEN-2019-068, Barton County Battery storage |
50.0 MW | Paused / redesign |
Barton, KS | SPP |
May 2019 | target 2029 |
Battery storage project GEN-2019-053, Edwards County Battery storage |
50.0 MW | Agreement signed |
Edwards, KS | SPP |
May 2019 | target 2028 |
Battery storage project GEN-2019-063, Ford County Battery storage |
50.0 MW | Agreement signed |
Ford, KS | SPP |
May 2019 | target 2028 |
Battery storage project GEN-2016-160, Ellis County Battery storage |
20.0 MW | Agreement signed |
Ellis, KS | SPP |
Nov 2016 | target 2026 |