United States β€Ί Grid β€Ί Interconnection queues β€Ί Kansas

OCTARY USA Β· INTERCONNECTION QUEUES

Battery storage interconnection queue in Kansas

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown315,745 MW
Active in queue5,745 MW31 requests
Agreement signed1,621 MW10 requests
Withdrawn324,544 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

31 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project GEN-2020-057, Finney County
Battery storage
425 MWAgreement signed Finney, KSSPP Apr 2020target 2030
Battery storage project GEN-2021-005, Saline County
Battery storage
350 MWAgreement signed Saline, KSSPP May 2021target 2030
Battery storage project GEN-2024-339, Leavenworth County
Battery storage
300 MWIn study Leavenworth, KSSPP Mar 2025target 2029
Battery storage project GEN-2025-SR16, Sumner County
Battery storage
300 MWIn study Sumner, KSSPP Jun 2025target 2026
Battery storage project GEN-2021-006, Labette County
Battery storage
300 MWIn study Labette, KSSPP May 2021target 2026
Battery storage project GEN-2021-029, Linn County
Battery storage
254 MWIn study Linn, KSSPP May 2021target 2026
Battery storage project GEN-2024-176, Reno County
Battery storage
250 MWIn study Reno, KSSPP Mar 2025target 2028
Battery storage project GEN-2024-330, Butler County
Battery storage
225 MWIn study Butler, KSSPP Mar 2025target 2028
Battery storage project GEN-2020-090, Bourbon County
Battery storage
204 MWIn study Bourbon, KSSPP Apr 2020target 2026
Battery storage project GEN-2017-227, Sedgwick County
Battery storage
202 MWAgreement signed Sedgwick, KSSPP Nov 2017target 2030
Battery storage project GEN-2023-037, Wyandotte County
Battery storage
200 MWIn study Wyandotte, KSSPP Oct 2023target 2028
Battery storage project GEN-2024-061, Cowley County
Battery storage
200 MWIn study Cowley, KSSPP Oct 2024target 2028
Battery storage project GEN-2022-024, Bourbon County
Battery storage
200 MWIn study Bourbon, KSSPP Jun 2022target 2028
Battery storage project GEN-2024-189, Ford County
Battery storage
199 MWIn study Ford, KSSPP Mar 2025target 2028
Battery storage project GEN-2024-320, Wyandotte County
Battery storage
199 MWIn study Wyandotte, KSSPP Mar 2025target 2028
Battery storage project GEN-2024-319, Wyandotte County
Battery storage
199 MWIn study Wyandotte, KSSPP Mar 2025target 2028
Battery storage project GEN-2024-121, Leavenworth County
Battery storage
199 MWIn study Leavenworth, KSSPP Mar 2025target 2028
Battery storage project ERAS-2025-029, Wyandotte County
Battery storage
170 MWIn study Wyandotte, KSSPP Oct 2025target 2027
Battery storage project GEN-2017-221, Sedgwick County
Battery storage
152 MWAgreement signed Sedgwick, KSSPP Nov 2017target 2026
Battery storage project GEN-2024-276, Shawnee County
Battery storage
150 MWIn study Shawnee, KSSPP Mar 2025target 2030
Battery storage project GEN-2021-103, Johnson County
Battery storage
150 MWAgreement signed Johnson, KSSPP May 2021target 2030
Battery storage project GEN-2025-SR4, Edwards County
Battery storage
150 MWIn study Edwards, KSSPP Aug 2025target 2028
Battery storage project GEN-2025-SR3, Clark County
Battery storage
150 MWIn study Clark, KSSPP Aug 2025target 2028
Battery storage project GEN-2024-277, Shawnee County
Battery storage
150 MWIn study Shawnee, KSSPP Mar 2025target 2030
Battery storage project GEN-2017-196, Johnson County
Battery storage
128 MWAgreement signed Johnson, KSSPP Nov 2017target 2030
Battery storage project GEN-2018-108, Barber County
Battery storage
95.0 MWAgreement signed Barber, KSSPP Nov 2018target 2028
Battery storage project GEN-2024-322, Graham County
Battery storage
75.0 MWIn study Graham, KSSPP Mar 2025target 2029
Battery storage project GEN-2019-068, Barton County
Battery storage
50.0 MWPaused / redesign Barton, KSSPP May 2019target 2029
Battery storage project GEN-2019-053, Edwards County
Battery storage
50.0 MWAgreement signed Edwards, KSSPP May 2019target 2028
Battery storage project GEN-2019-063, Ford County
Battery storage
50.0 MWAgreement signed Ford, KSSPP May 2019target 2028
Battery storage project GEN-2016-160, Ellis County
Battery storage
20.0 MWAgreement signed Ellis, KSSPP Nov 2016target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)