Gas project J4113, Cerro Gordo County Gas |
1,315 MW | In study |
Cerro Gordo, IA | MISO |
Oct 2025 | target 2028 |
Gas project E0050, Linn County Gas Β· Interstate Power and Light Company (IPL) |
987 MW | In study |
Linn, IA | MISO |
Nov 2025 | target 2028 |
Gas project E0049, Cerro Gordo County Gas Β· Interstate Power and Light Company (IPL) |
798 MW | In study |
Cerro Gordo, IA | MISO |
Oct 2025 | target 2028 |
Gas project E0010, Marshall County Gas Β· Interstate Power and Light Company (IPL) |
798 MW | In study |
Marshall, IA | MISO |
Aug 2025 | target 2028 |
Nuclear project J3932, Linn County Nuclear |
646 MW | In study |
Linn, IA | MISO |
Mar 2025 | target 2029 |
Gas project J4114, Washington County Gas |
525 MW | In study |
Washington, IA | MISO |
Oct 2025 | target 2030 |
Onshore wind project E0015, Franklin County Onshore wind Β· Interstate Power and Light Company (IPL) |
360 MW | In study |
Franklin, IA | MISO |
Aug 2025 | target 2028 |
Onshore wind project J4056, Marshall County Onshore wind |
310 MW | In study |
Marshall, IA | MISO |
Aug 2025 | target 2030 |
Onshore wind project J4006, Ringgold County Onshore wind |
290 MW | In study |
Ringgold, IA | MISO |
May 2025 | target 2030 |
Orient Energy Center Gas Β· MidAmerican Energy Company |
265 MW | In study |
Adair, IA | MISO |
Aug 2025 | target 2027 |
Surplus; J500 Gas |
263 MW | In study |
Adair, IA | MISO |
Jul 2025 | target 2027 |
Replacing 244 MW of Solar with Nuclear; Duane Arnold Nuclear |
251 MW | In study |
Linn, IA | MISO |
Aug 2025 | target 2029 |
Solar project J3911, Louisa County Solar |
250 MW | In study |
Louisa, IA | MISO |
Feb 2025 | target 2030 |
Onshore wind project J4068, Marshall County Onshore wind |
232 MW | In study |
Marshall, IA | MISO |
Oct 2025 | target 2030 |
Surplus; J449 Battery storage |
202 MW | In study |
Mitchell, IA | MISO |
Mar 2025 | target 2027 |
Surplus; J1190 Battery storage |
200 MW | In study |
Clinton, IA | MISO |
Jul 2025 | target 2026 |
Surplus; J416 Battery storage |
200 MW | In study |
Franklin, IA | MISO |
Aug 2025 | target 2026 |
Replacing 200 MW of Solar with Nuclear; J1444 Nuclear |
200 MW | In study |
Linn, IA | MISO |
Aug 2025 | target 2029 |
Battery storage project J4173, Wapello County Battery storage |
199 MW | In study |
Wapello, IA | MISO |
Oct 2025 | target 2028 |
Battery storage project J4155, Linn County Battery storage |
195 MW | In study |
Linn, IA | MISO |
Oct 2025 | target 2029 |
Onshore wind project J3926, Webster County Onshore wind |
170 MW | In study |
Webster, IA | MISO |
Mar 2025 | target 2030 |
Solar project J2757, Cherokee County Solar |
160 MW | In study |
Cherokee, IA | MISO |
Oct 2025 | target 2026 |
Solar project J3137, Pocahontas County Solar |
156 MW | In study |
Pocahontas, IA | MISO |
Oct 2025 | target 2026 |
Onshore wind project J3898, Howard County Onshore wind |
155 MW | In study |
Howard, IA | MISO |
Feb 2025 | target 2030 |
Replacing 150 MW of coal generation with BESS at Lansing; Lansing 4 Battery storage |
150 MW | In study |
Allamakee, IA | MISO |
Apr 2025 | target 2026 |
Solar project J3107, Johnson County Solar |
150 MW | In study |
Johnson, IA | MISO |
Oct 2025 | target 2025 |
Replacing 130 MW of coal generation with BESS at Lansing; Lansing 4 Battery storage |
130 MW | In study |
Allamakee, IA | MISO |
Apr 2025 | target 2026 |
Solar project J4086, Wapello County Solar |
120 MW | In study |
Wapello, IA | MISO |
Oct 2025 | target 2029 |
Replacing 100 MW of Solar with Nuclear; Duane Arnold Nuclear |
100 MW | In study |
Linn, IA | MISO |
Aug 2025 | target 2029 |
Solar project J4037, Franklin County Solar |
100 MW | In study |
Franklin, IA | MISO |
Jun 2025 | target 2030 |
Battery storage project J4172, Wapello County Battery storage |
99.0 MW | In study |
Wapello, IA | MISO |
Oct 2025 | target 2028 |
Gas project J4145, Cerro Gordo County Gas |
98.0 MW | In study |
Cerro Gordo, IA | MISO |
Oct 2025 | target 2028 |
Surplus; J495 Battery storage |
75.0 MW | In study |
Kossuth, IA | MISO |
Jul 2025 | target 2026 |
Replacing 50 MW of Solar with Nuclear; Duane Arnold Nuclear |
64.0 MW | In study |
Linn, IA | MISO |
Aug 2025 | target 2029 |
Solar project J4150, Cass County Solar |
42.2 MW | In study |
Cass, IA | MISO |
Oct 2025 | target 2027 |