Withdrawn queue requests in Indiana (2022 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown10416.2 GW
Active in queue13.5 GW71 requests
Agreement signed50.0 MW1 requests
Withdrawn10416.2 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

104 requests ยท page 1 of 3
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project LGE-GIS-2022-005, Clarke County
Solar + storage
1,400 MWWithdrawn / abandoned Clarke, INSoutheast Jul 2022target 2029
Solar + storage project LGE-GIS-2022-006, Clarke County
Solar + storage
1,000 MWWithdrawn / abandoned Clarke, INSoutheast Aug 2022target 2029
Gas project J3215, Laporte County
Gas
594 MWWithdrawn / abandoned Laporte, INMISO Sep 2022target 2025
Battery storage project J2443, Kosciusko County
Battery storage
500 MWWithdrawn / abandoned Kosciusko, INMISO Sep 2022target 2025
Solar + storage project J3119, Pulaski County
Solar + storage
350 MWWithdrawn / abandoned Pulaski, INMISO Sep 2022target 2026
Solar project J2269, Fountain County
Solar
300 MWWithdrawn / abandoned Fountain, INMISO Jun 2022target 2024
Solar + storage project J3113, Greene County
Solar + storage
300 MWWithdrawn / abandoned Greene, INMISO Sep 2022target 2026
Solar + storage project J2687, Hancock County
Solar + storage
300 MWWithdrawn / abandoned Hancock, INMISO Sep 2022target 2026
Onshore wind project J2132, Vermillion County
Onshore wind
300 MWWithdrawn / abandoned Vermillion, INMISO Oct 2022target 2024
Solar project J2798, White County
Solar
250 MWWithdrawn / abandoned White, INMISO Sep 2022target 2026
Battery storage project J2498, Hamilton County
Battery storage
250 MWWithdrawn / abandoned Hamilton, INMISO Sep 2022target 2026
Solar project J2507, Pike County
Solar
250 MWWithdrawn / abandoned Pike, INMISO Sep 2022target 2025
Onshore wind project J2723, Vermillion County
Onshore wind
249 MWWithdrawn / abandoned Vermillion, INMISO Sep 2022target 2027
Battery storage project J2585, Greene County
Battery storage
240 MWWithdrawn / abandoned Greene, INMISO Sep 2022target 2025
Solar + storage project J2650, Hancock County
Solar + storage
236 MWWithdrawn / abandoned Hancock, INMISO Sep 2022target 2027
Solar project J2695, Carroll County
Solar
234 MWWithdrawn / abandoned Carroll, INMISO Sep 2022target 2027
Solar project J2709, Miami County
Solar
228 MWWithdrawn / abandoned Miami, INMISO Sep 2022target 2027
Solar project J2513, Vigo County
Solar
220 MWWithdrawn / abandoned Vigo, INMISO Sep 2022target 2025
Battery storage project AI2-023, Lake County
Battery storage
200 MWWithdrawn / abandoned Lake, INPJM Dec 2022target 2028
Solar + storage project J2959, Starke County
Solar + storage
200 MWWithdrawn / abandoned Starke, INMISO Sep 2022target 2027
Solar project J3146, Putnam County
Solar
200 MWWithdrawn / abandoned Putnam, INMISO Sep 2022target 2027
Battery storage project J2421, Rush County
Battery storage
200 MWWithdrawn / abandoned Rush, INMISO Sep 2022target 2025
Battery storage project J2823, Jefferson County
Battery storage
200 MWWithdrawn / abandoned Jefferson, INMISO Sep 2022target 2025
Solar + storage project AI1-078, Laporte County
Solar + storage
200 MWWithdrawn / abandoned Laporte, INPJM Jul 2022target 2026
Solar project J2226, Newton County
Solar
200 MWWithdrawn / abandoned Newton, INMISO Jun 2022target 2024
Solar project J2573, Daviess County
Solar
200 MWWithdrawn / abandoned Daviess, INMISO Sep 2022target 2026
Solar project J2664, Montgomery County
Solar
200 MWWithdrawn / abandoned Montgomery, INMISO Sep 2022target 2026
Solar project J2805, Fountain County
Solar
200 MWWithdrawn / abandoned Fountain, INMISO Sep 2022target 2026
Onshore wind project J1966, Clinton County
Onshore wind
200 MWWithdrawn / abandoned Clinton, INMISO Mar 2022target 2025
Solar project J2407, Sullivan County
Solar
198 MWWithdrawn / abandoned Sullivan, INMISO Sep 2022target 2027
Solar project J2130, Vermillion County
Solar
180 MWWithdrawn / abandoned Vermillion, INMISO Mar 2022target 2024
Solar project J1815, Montgomery County
Solar
180 MWWithdrawn / abandoned Montgomery, INMISO Mar 2022target 2023
Solar project J2512, Kosciusko County
Solar
173 MWWithdrawn / abandoned Kosciusko, INMISO Sep 2022target 2025
Battery storage project J2530, Clinton County
Battery storage
170 MWWithdrawn / abandoned Clinton, INMISO Sep 2022target 2026
Solar project J2539, Clark County
Solar
150 MWWithdrawn / abandoned Clark, INMISO Sep 2022target 2026
Solar + storage project J3225, Laporte County
Solar + storage
150 MWWithdrawn / abandoned Laporte, INMISO Sep 2022target 2026
Solar + storage project J3016, Cass County
Solar + storage
150 MWWithdrawn / abandoned Cass, INMISO Sep 2022target 2027
Solar + storage project J2960, Spencer County
Solar + storage
150 MWWithdrawn / abandoned Spencer, INMISO Sep 2022target 2027
Solar project J2212, Jefferson County
Solar
150 MWWithdrawn / abandoned Jefferson, INMISO Mar 2022target 2025
Solar project J3103, Fountain County
Solar
145 MWWithdrawn / abandoned Fountain, INMISO Jun 2022target 2026
Solar + storage project J2615, Warren County
Solar + storage
145 MWWithdrawn / abandoned Warren, INMISO Sep 2022target 2026
Onshore wind project J2919, Montgomery County
Onshore wind
143 MWWithdrawn / abandoned Montgomery, INMISO Sep 2022target 2027
Solar project AH2-213, Randolph County
Solar
140 MWWithdrawn / abandoned Randolph, INPJM Mar 2022target 2026
Solar project J1876, Decatur County
Solar
140 MWWithdrawn / abandoned Decatur, INMISO Mar 2022target 2024
Battery storage project J2418, Marshall County
Battery storage
140 MWWithdrawn / abandoned Marshall, INMISO Sep 2022target 2025
Solar + storage project J3226, Marshall County
Solar + storage
130 MWWithdrawn / abandoned Marshall, INMISO Sep 2022target 2026
Solar project AH2-237, Wells County
Solar
125 MWWithdrawn / abandoned Wells, INPJM Mar 2022target 2026
Battery storage project J2775, White County
Battery storage
125 MWWithdrawn / abandoned White, INMISO Sep 2022target 2025
Solar project J2711, Porter County
Solar
122 MWWithdrawn / abandoned Porter, INMISO Sep 2022target 2027
Solar + storage project J2895, Clark County
Solar + storage
120 MWWithdrawn / abandoned Clark, INMISO Sep 2022target 2025
Page 1 of 3

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)