OCTARY USA Β· INTERCONNECTION QUEUESWithdrawn queue requests in Indiana (2019 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar + storage project AE2-130, Spencer County Solar + storage Β· Sand Ridge Solar Project LLC |
800 MW | Withdrawn / abandoned |
| Gas project J1288, Vermillion County Gas |
667 MW | Withdrawn / abandoned |
| Paddlefish Solar Solar + storage |
350 MW | Withdrawn / abandoned |
| Solar project J1419, Greene County Solar |
250 MW | Withdrawn / abandoned |
| Solar project J1447, Porter County Solar |
250 MW | Withdrawn / abandoned |
| Onshore wind project AE2-154, White County Onshore wind |
250 MW | Withdrawn / abandoned |
| Solar project J1412, Porter County Solar |
250 MW | Withdrawn / abandoned |
| Battery storage project AE2-332, Elkhart County Battery storage |
209 MW | Withdrawn / abandoned |
| Solar project J1457, Vermillion County Solar |
200 MW | Withdrawn / abandoned |
| Solar project J1332, Jasper County Solar |
200 MW | Withdrawn / abandoned |
| Solar project J1296, Gibson County Solar |
200 MW | Withdrawn / abandoned |
| Solar project AF1-298, Delaware County Solar |
200 MW | Withdrawn / abandoned |
| Solar project AF1-221, Franklin County Solar Β· Yellow Perch Solar LLC |
180 MW | Withdrawn / abandoned |
| Solar project J1356, Martin County Solar |
160 MW | Withdrawn / abandoned |
| Solar + storage project AF1-148, Wells County Solar + storage |
159 MW | Withdrawn / abandoned |
| Solar + storage project AF1-175, St. Joseph County Solar + storage |
152 MW | Withdrawn / abandoned |
| Battery storage project J1353, Lake County Battery storage |
150 MW | Withdrawn / abandoned |
| Solar project J1398, Pike County Solar |
150 MW | Withdrawn / abandoned |
| Solar project J1254, Knox County Solar |
150 MW | Withdrawn / abandoned |
| Solar project AE2-090, Randolph County Solar |
144 MW | Withdrawn / abandoned |
| Solar project J1405, Greene County Solar |
140 MW | Withdrawn / abandoned |
| Solar project J1227, Spencer County Solar |
125 MW | Withdrawn / abandoned |
| Solar project J1385, Hendricks County Solar |
100 MW | Withdrawn / abandoned |
| Solar + storage project J1274, Posey County Solar + storage |
100 MW | Withdrawn / abandoned |
| Solar + storage project J1276, Posey County Solar + storage |
100 MW | Withdrawn / abandoned |
| Battery storage project J1271, Vanderburgh County Battery storage |
100 MW | Withdrawn / abandoned |
| Solar project J1273, Marshall County Solar |
100 MW | Withdrawn / abandoned |
| Solar project J1342, Starke County Solar |
99.0 MW | Withdrawn / abandoned |
| Thalassa Energy Project Solar |
96.0 MW | Withdrawn / abandoned |
| Battery storage project AF1-046, Elkhart County Battery storage |
52.2 MW | Withdrawn / abandoned |
| Battery storage project AE2-170, Delaware County Battery storage |
50.0 MW | Withdrawn / abandoned |
| Solar project J1265, Lagrange County Solar |
43.0 MW | Withdrawn / abandoned |
| Solar project AF1-313, Delaware County Solar |
40.0 MW | Withdrawn / abandoned |
| Battery storage project J1233, Pike County Battery storage |
32.5 MW | Withdrawn / abandoned |
| Battery storage project AE2-171, Madison County Battery storage |
30.0 MW | Withdrawn / abandoned |
| Solar project J1318, Rush County Solar |
25.0 MW | Withdrawn / abandoned |
| Battery storage project AF1-080, Madison County Battery storage |
20.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)