πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Indiana

BATTERY STORAGE Β· MISO

Battery storage project J1233, Pike County

Battery storage project J1233, Pike County is a 32.5 MW battery storage request withdrawn in the MISO interconnection queue, in Pike County, Indiana, connecting to Southern Indiana Gas & Electric Company d/b/a Vectren Energy Delivery of Indiana, Inc..

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2019 (completed)
  2. Withdrawn / abandonedFeb 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J1233
Grid region
MISO (Midcontinent)
Utility / transmission owner
Southern Indiana Gas & Electric Company d/b/a Vectren Energy Delivery of Indiana, Inc.
Connection point (POI)
Cato 138 kV Substation
Location
Pike County, Indiana
Technology
Battery: 32.5 MW
Total requested
32.5 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
29 April 2019
Proposed online date
October 2023
Withdrawn
February 2023

Location

Marker shows the centre of Pike County; the queue data does not give exact sites.

Power plants in Indiana Β· Transmission lines in Indiana

Other requests in Pike County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem