Battery storage interconnection queue in Illinois

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown10316.7 GW
Active in queue16.7 GW103 requests
Agreement signed170 MW4 requests
Withdrawn10712.7 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

103 requests ยท page 1 of 3
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project AH2-416, Livingston County
Battery storage
450 MWIn study Livingston, ILPJM Mar 2022target 2026
Battery storage project AG2-545, Mchenry County
Battery storage ยท Monarch Grid, LLC
400 MWIn study Mchenry, ILPJM Mar 2025target 2024
Battery storage project AJ1-012, Lake County
Battery storage
354 MWIn study Lake, ILPJM May 2023target 2027
Battery storage project AJ1-011, Lake County
Battery storage
328 MWIn study Lake, ILPJM May 2023target 2027
Battery storage project J3946, Tazewell County
Battery storage
300 MWIn study Tazewell, ILMISO Mar 2025target 2030
Battery storage project AI1-024, Mclean County
Battery storage
300 MWIn study Mclean, ILPJM Apr 2022target 2026
Battery storage project J2377, Peoria County
Battery storage
300 MWIn study Peoria, ILMISO Nov 2024target 2028
Battery storage project J2647, Franklin County
Battery storage
300 MWIn study Franklin, ILMISO Sep 2022target 2028
Battery storage project AH2-415, Livingston County
Battery storage
300 MWIn study Livingston, ILPJM Mar 2022target 2026
Battery storage project J3558, Champaign County
Battery storage
300 MWIn study Champaign, ILMISO Apr 2024target 2027
Battery storage project J3525, Rock Island County
Battery storage
300 MWIn study Rock Island, ILMISO Apr 2024target 2028
Battery storage project J3216, Peoria County
Battery storage
300 MWIn study Peoria, ILMISO Sep 2022target 2027
Battery storage project J3417, Macon County
Battery storage
300 MWIn study Macon, ILMISO Apr 2024target 2028
Battery storage project AJ1-014, Will County
Battery storage
260 MWIn study Will, ILPJM May 2023target 2027
Battery storage project J3883, Crawford County
Battery storage
250 MWIn study Crawford, ILMISO Feb 2025target 2030
Battery storage project J4198, Christian County
Battery storage
250 MWIn study Christian, ILMISO Sep 2025target 2030
Battery storage project AI1-149, Mchenry County
Battery storage
250 MWIn study Mchenry, ILPJM Sep 2022target 2025
Battery storage project AJ1-013, Will County
Battery storage
250 MWIn study Will, ILPJM May 2023target 2027
Battery storage project J4118, Mclean County
Battery storage
250 MWIn study Mclean, ILMISO Sep 2025target 2030
Battery storage project AI1-154, Will County
Battery storage
230 MWIn study Will, ILPJM Sep 2022target 2027
Battery storage project AH2-421, Grundy County
Battery storage
230 MWIn study Grundy, ILPJM Mar 2022target 2025
Battery storage project J3727, Madison County
Battery storage
225 MWIn study Madison, ILMISO Apr 2024target 2028
Battery storage project J4204, Marion County
Battery storage
200 MWIn study Marion, ILMISO target 2031
Battery storage project J4199, Fulton County
Battery storage
200 MWIn study Fulton, ILMISO Sep 2025target 2029
Battery storage project J3031, Jefferson County
Battery storage
200 MWIn study Jefferson, ILMISO Sep 2022target 2026
Battery storage project J2402, Johnson County
Battery storage
200 MWIn study Johnson, ILMISO Sep 2022target 2025
Battery storage project J3296, Hamilton County
Battery storage
200 MWIn study Hamilton, ILMISO Apr 2024target 2027
Battery storage project J3497, Pulaski County
Battery storage
200 MWIn study Pulaski, ILMISO Apr 2024target 2028
Battery storage project J2587, Edgar County
Battery storage
200 MWIn study Edgar, ILMISO Sep 2022target 2025
Battery storage project J3881, Clay County
Battery storage
200 MWIn study Clay, ILMISO Feb 2025target 2030
Battery storage project J3660, Rock Island County
Battery storage
200 MWIn study Rock Island, ILMISO Apr 2024target 2028
Surplus; J1712
Battery storage
200 MWIn study Perry, ILMISO Apr 2025target 2027
Battery storage project J2607, Montgomery County
Battery storage
200 MWIn study Montgomery, ILMISO Sep 2022target 2026
Battery storage project J4002, Edgar County
Battery storage
200 MWIn study Edgar, ILMISO Apr 2025target 2030
Battery storage project J2998, St. Clair County
Battery storage
200 MWIn study St. Clair, ILMISO Sep 2022target 2025
Battery storage project J3298, Tazewell County
Battery storage
200 MWIn study Tazewell, ILMISO Apr 2024target 2027
Battery storage project J3729, Franklin County
Battery storage
200 MWIn study Franklin, ILMISO Apr 2024target 2028
Battery storage project J2379, Clay County
Battery storage
200 MWIn study Clay, ILMISO Sep 2022target 2026
Riverbank Energy
Battery storage ยท Lincoln Reserve Energy, LLC
200 MWIn study Cook, ILPJM Mar 2020target 2024
Battery storage project J2532, Sangamon County
Battery storage
200 MWIn study Sangamon, ILMISO Sep 2022target 2026
Battery storage project AI1-023, Mclean County
Battery storage
200 MWIn study Mclean, ILPJM Apr 2022target 2026
Battery storage project J4137, Pulaski County
Battery storage
200 MWIn study Pulaski, ILMISO Sep 2025target 2030
Battery storage project J3947, Shelby County
Battery storage
200 MWIn study Shelby, ILMISO Mar 2025target 2030
Battery storage project AG2-544, Mchenry County
Battery storage ยท Monarch Grid, LLC
200 MWIn study Mchenry, ILPJM Mar 2025target 2024
Battery storage project J3515, Sangamon County
Battery storage
200 MWIn study Sangamon, ILMISO Apr 2024target 2026
Battery storage project J2575, Tazewell County
Battery storage
198 MWIn study Tazewell, ILMISO Sep 2022target 2027
Battery storage project J3517, Williamson County
Battery storage
190 MWIn study Williamson, ILMISO Apr 2024target 2028
Battery storage project J3904, Tazewell County
Battery storage
175 MWIn study Tazewell, ILMISO Mar 2025target 2030
Battery storage project AH2-259, Kendall County
Battery storage
172 MWIn study Kendall, ILPJM Mar 2022target 2024
Battery storage project AH2-204, Stephenson County
Battery storage
170 MWIn study Stephenson, ILPJM Mar 2022target 2026
Page 1 of 3

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)