United States β€Ί Grid β€Ί Interconnection queues β€Ί Florida

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Florida (2024 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown212,072 MW
Active in queue2,072 MW21 requests
Agreement signed0.0 MW0 requests
Withdrawn285,054 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

21 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project 620, Bay County
Battery storage Β· FPL
400 MWIn study Bay, FLSoutheast Jan 2024target 2026
Battery storage project 615, Putnam County
Battery storage Β· FPL
200 MWIn study Putnam, FLSoutheast Jan 2024target 2027
Battery storage project FC100009, Pasco County
Battery storage Β· Duke Energy Florida, LLC
199 MWIn study Pasco, FLSoutheast Dec 2024target 2029
Battery storage project FC100008, Highlands County
Battery storage Β· Duke Energy Florida, LLC
100 MWIn study Highlands, FLSoutheast Dec 2024target 2029
Solar project 344, Madison County
Solar Β· Duke Energy Florida, LLC
74.9 MWUnder construction Madison, FLSoutheast Jan 2024target 2026
Solar project 343, Orange County
Solar Β· Duke Energy Florida, LLC
74.9 MWUnder construction Orange, FLSoutheast Jan 2024target 2028
Solar project FC100007, Madison County
Solar Β· Duke Energy Florida, LLC
74.9 MWIn study Madison, FLSoutheast Nov 2024target 2028
Solar project FC100018, Liberty County
Solar Β· Duke Energy Florida, LLC
74.9 MWIn study Liberty, FLSoutheast Dec 2024target 2028
Solar project 342, Orange County
Solar Β· Duke Energy Florida, LLC
74.9 MWUnder construction Orange, FLSoutheast Jan 2024target 2027
Solar + storage project JEA-Q012, Duval County
Solar + storage
74.9 MWIn study Duval, FLSoutheast May 2024target 2027
Solar + storage project JEA-Q010, Duval County
Solar + storage
74.9 MWIn study Duval, FLSoutheast May 2024target 2026
Solar project FC100012, Hamilton County
Solar Β· Duke Energy Florida, LLC
74.9 MWIn study Hamilton, FLSoutheast Nov 2024target 2028
Solar project FC100004, Sumter County
Solar Β· Duke Energy Florida, LLC
74.9 MWIn study Sumter, FLSoutheast Nov 2024target 2028
Solar project 341, Orange County
Solar Β· Duke Energy Florida, LLC
74.9 MWUnder construction Orange, FLSoutheast Jan 2024target 2026
Solar + storage project JEA-Q011, Duval County
Solar + storage
74.9 MWIn study Duval, FLSoutheast May 2024target 2026
Solar project FC100006, Madison County
Solar Β· Duke Energy Florida, LLC
74.9 MWIn study Madison, FLSoutheast Nov 2024target 2028
Storey Bend South
Solar
74.5 MWIn study Osceola, FLSoutheast Feb 2024target 2026
Solar project 112, Hillsborough County
Solar
74.5 MWIn study Hillsborough, FLSoutheast Mar 2024target 2026
Taylor Creek Two
Solar
60.0 MWIn study Orange, FLSoutheast Feb 2024target 2026
Solar project 111, Polk County
Solar
52.0 MWIn study Polk, FLSoutheast Mar 2024target 2027
Other project FC100000, Pasco County
Other Β· Masked
13.1 MWIn study Pasco, FLSoutheast Dec 2024target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)