United States βΊ Grid βΊ Interconnection queues βΊ Connecticut
OCTARY USA Β· INTERCONNECTION QUEUESWithdrawn queue requests in Connecticut (2018 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Offshore Wind Offshore wind |
805 MW | Withdrawn / abandoned |
| Offshore Wind Offshore wind |
805 MW | Withdrawn / abandoned |
| NTE Connecticut Gas |
672 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
200 MW | Withdrawn / abandoned |
| Solar Solar |
50.0 MW | Withdrawn / abandoned |
| Solar Solar |
26.4 MW | Withdrawn / abandoned |
| Solar Solar |
24.6 MW | Withdrawn / abandoned |
| Solar Solar |
20.0 MW | Withdrawn / abandoned |
| Solar Solar |
20.0 MW | Withdrawn / abandoned |
| Solar Solar |
20.0 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
20.0 MW | Withdrawn / abandoned |
| Solar Solar |
19.9 MW | Withdrawn / abandoned |
| Black Hill Point Energy Center Solar |
19.9 MW | Withdrawn / abandoned |
| Solar Solar |
19.9 MW | Withdrawn / abandoned |
| Fuel Cell Other |
14.8 MW | Withdrawn / abandoned |
| Solar Solar |
7.5 MW | Withdrawn / abandoned |
| Solar Solar |
6.0 MW | Withdrawn / abandoned |
| Solar Solar |
5.0 MW | Withdrawn / abandoned |
| Generator Increase Other |
2.1 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)