United States βΊ Grid βΊ Interconnection queues βΊ Connecticut
OFFSHORE WIND Β· ISO-NEOffshore Wind
Offshore Wind is a 805 MW offshore wind request withdrawn in the ISO-NE interconnection queue.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2018 (completed)
- Withdrawn / abandonedJan 2022 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 792
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- Eversource (CL&P) 345kV Montville, alternatively Eversource (CL&P) 345kV Millstone
- Location
- Connecticut
- Technology
- Offshore Wind: 805 MW
- Total requested
- 805 MW
- Service type
- Network resource (NRIS)
- Study phase
- Not Started
- Queue status
- Withdrawn
- Entered queue
- 19 October 2018
- Proposed online date
- May 2023
- Withdrawn
- January 2022
Location
No county location in the queue data.
Power plants in Connecticut Β· Transmission lines in Connecticut
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem