SOLAR Β· ISO-NE

Solar

Solar is a 50.0 MW solar request withdrawn in the ISO-NE interconnection queue, in Hartford County, Connecticut.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2018 (completed)
  2. Withdrawn / abandonedDec 2018 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
796
Grid region
ISO-NE (New England)
Connection point (POI)
Tap of existing 115 kV Connecticut Light & Power Company line between Barbour Hill and Windsor Locks
Location
Hartford County, Connecticut
Technology
Solar: 50.0 MW
Total requested
50.0 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
26 October 2018
Proposed online date
November 2022
Withdrawn
December 2018

Location

No county location in the queue data.

Power plants in Connecticut Β· Transmission lines in Connecticut

Other requests in Hartford County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem