Requests shown151,300 MW
Active in queue453 MW3 requests
Agreement signed72.5 MW1 requests
Withdrawn151,300 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

15 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project J899, Carroll County
Onshore wind
180 MWWithdrawn / abandoned Carroll, ARMISO Jun 2017target 2019
Solar project J698, Chicot County
Solar
150 MWWithdrawn / abandoned Chicot, ARMISO Jun 2017target 2015
Solar project J858, Bradley County
Solar
140 MWWithdrawn / abandoned Bradley, ARMISO Jun 2017target 2019
Solar project J942, Craighead County
Solar
107 MWWithdrawn / abandoned Craighead, ARMISO Jun 2017target 2021
Solar project J902, Ashley County
Solar
100 MWWithdrawn / abandoned Ashley, ARMISO Jun 2017target 2019
Solar project J904, Ashley County
Solar
100 MWWithdrawn / abandoned Ashley, ARMISO Jun 2017target 2019
Solar project J922, Chicot County
Solar
100 MWWithdrawn / abandoned Chicot, ARMISO Jun 2017target 2020
Solar project J948, Poinsett County
Solar
100 MWWithdrawn / abandoned Poinsett, ARMISO Jun 2017target 2020
Solar project J822, Lonoke County
Solar
100 MWWithdrawn / abandoned Lonoke, ARMISO Jun 2017target 2019
Solar project GEN-2017-076, Benton County
Solar
52.2 MWWithdrawn / abandoned Benton, ARSPP May 20172024
Battery storage project J924, Monroe County
Battery storage
50.0 MWWithdrawn / abandoned Monroe, ARMISO Jun 2017target 2020
Solar project J894, Woodruff County
Solar
45.0 MWWithdrawn / abandoned Woodruff, ARMISO Jun 2017target 2020
Solar project J895, Lonoke County
Solar
33.0 MWWithdrawn / abandoned Lonoke, ARMISO Jun 2017target 2020
Solar project GEN-2017-003, Little River County
Solar
21.6 MWWithdrawn / abandoned Little River, ARSPP Jan 2017target 2018
Solar project GEN-2017-002, Sebastian County
Solar
21.6 MWWithdrawn / abandoned Sebastian, ARSPP Jan 2017target 2018

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)