United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Southeast (non-ISO utilities) (2022 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown21128.0 GW
Active in queue17.0 GW142 requests
Agreement signed5,225 MW33 requests
Withdrawn21128.0 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

211 requests Β· page 1 of 5
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project 566988, Oconee County
Battery storage
1,680 MWWithdrawn / abandoned Oconee, SCSoutheast Jun 2022
Solar + storage project LGE-GIS-2022-005, Clarke County
Solar + storage
1,400 MWWithdrawn / abandoned Clarke, INSoutheast Jul 2022target 2029
Solar + storage project LGE-GIS-2022-006, Clarke County
Solar + storage
1,000 MWWithdrawn / abandoned Clarke, INSoutheast Aug 2022target 2029
Gas project 569364, Cherokee County
Gas
757 MWWithdrawn / abandoned Cherokee, SCSoutheast Jun 2022
Gas project 564266, Cherokee County
Gas
757 MWWithdrawn / abandoned Cherokee, SCSoutheast Jun 2022
Gas project LGE-GIS-2022-011, Mercer County
Gas
660 MWWithdrawn / abandoned Mercer, KYSoutheast Oct 2022target 2028
Gas project LGE-GIS-2022-004, Mercer County
Gas
660 MWWithdrawn / abandoned Mercer, KYSoutheast Jun 2022target 2027
Gas project 567758, Davidson County
Gas
500 MWWithdrawn / abandoned Davidson, NCSoutheast Jun 2022
Gas project GI-99, Butler County
Gas
470 MWWithdrawn / abandoned Butler, MOSoutheast Jul 2022target 2026
Gas project GI-105, Osage County
Gas
460 MWWithdrawn / abandoned Osage, OKSoutheast Jul 2022target 2025
Solar + storage project 520, Panola County
Solar + storage
400 MWWithdrawn / abandoned Panola, MSSoutheast Sep 2022target 2024
Solar project GI-97, New Madrid County
Solar
350 MWWithdrawn / abandoned New Madrid, MOSoutheast Jan 2022target 2024
Solar project GI-106, New Madrid County
Solar
350 MWWithdrawn / abandoned New Madrid, MOSoutheast Aug 2022target 2024
Onshore wind project GI-112, Craig County
Onshore wind
300 MWWithdrawn / abandoned Craig, OKSoutheast Nov 2022target 2026
Solar project 569986, Richmond County
Solar Β· Masked
275 MWWithdrawn / abandoned Richmond, NCSoutheast Jun 2022
Solar + storage project GI-108, Craig County
Solar + storage
250 MWWithdrawn / abandoned Craig, OKSoutheast Aug 2022target 2025
Solar project GI-98, New Madrid County
Solar
250 MWWithdrawn / abandoned New Madrid, MOSoutheast Jan 2022target 2024
Solar project IC-1018, Mcduffie County
Solar
250 MWWithdrawn / abandoned Mcduffie, GASoutheast Feb 2022
Battery storage project 524, Jefferson County
Battery storage
250 MWWithdrawn / abandoned Jefferson, TNSoutheast Oct 2022
Solar project GI-107, New Madrid County
Solar
250 MWWithdrawn / abandoned New Madrid, MOSoutheast Aug 2022target 2024
Solar project IC-1082, Jefferson County
Solar
225 MWWithdrawn / abandoned Jefferson, ALSoutheast Oct 2022
Battery storage project LGE-GIS-2022-010, Bell County
Battery storage
216 MWWithdrawn / abandoned Bell, KYSoutheast Sep 2022target 2030
Solar project 500, Mccracken County
Solar
200 MWWithdrawn / abandoned Mccracken, KYSoutheast May 2022
Battery storage project IC-1041, Fulton County
Battery storage
200 MWWithdrawn / abandoned Fulton, GASoutheast Jul 2022
Solar project 566096, Marlboro County
Solar Β· Masked
200 MWWithdrawn / abandoned Marlboro, SCSoutheast Jun 2022
Solar + storage project 525, Lawrence County
Solar + storage
200 MWWithdrawn / abandoned Lawrence, ALSoutheast Nov 2022
Battery storage project IC-1032, Mitchell County
Battery storage
200 MWWithdrawn / abandoned Mitchell, GASoutheast Mar 2022
Solar + storage project 521, Colbert County
Solar + storage
200 MWWithdrawn / abandoned Colbert, ALSoutheast Sep 2022target 2026
Solar + storage project 508, Choctaw County
Solar + storage
200 MWWithdrawn / abandoned Choctaw, MSSoutheast Jul 2022target 2026
Solar project 502, Noxubee County
Solar
200 MWWithdrawn / abandoned Noxubee, MSSoutheast May 2022
Solar project 569030, Pender County
Solar Β· Masked
200 MWWithdrawn / abandoned Pender, NCSoutheast Jun 2022
Battery storage project 568550, Greenwood County
Battery storage
197 MWWithdrawn / abandoned Greenwood, SCSoutheast Jun 2022
Solar project 568608, Wake County
Solar Β· Duke Energy Progress, LLC
187 MWWithdrawn / abandoned Wake, NCSoutheast Jun 2022
Solar + storage project 506, Alcorn County
Solar + storage
186 MWWithdrawn / abandoned Alcorn, MSSoutheast Jun 2022
Solar project 568672, Davie County
Solar
176 MWWithdrawn / abandoned Davie, NCSoutheast Jun 2022
Solar project 569290, Jones County
Solar Β· Duke Energy Progress, LLC
172 MWWithdrawn / abandoned Jones, NCSoutheast Jun 2022
Solar + storage project 498, Colbert County
Solar + storage
170 MWWithdrawn / abandoned Colbert, ALSoutheast Apr 2022target 2027
Solar project 507, Grundy County
Solar
160 MWWithdrawn / abandoned Grundy, TNSoutheast Jul 2022
Solar project 565542, Wayne County
Solar Β· Masked
160 MWWithdrawn / abandoned Wayne, NCSoutheast Jun 2022
Solar + storage project 173B, Lexington County
Solar + storage
152 MWWithdrawn / abandoned Lexington, SCSoutheast Feb 2022
Solar project 568598, Wake County
Solar Β· Duke Energy Progress, LLC
152 MWWithdrawn / abandoned Wake, NCSoutheast Jun 2022
Solar project 183, Kershaw County
Solar
150 MWWithdrawn / abandoned Kershaw, SCSoutheast Apr 2022target 2024
Solar + storage project 516, Lauderdale County
Solar + storage
150 MWWithdrawn / abandoned Lauderdale, ALSoutheast Aug 2022target 2024
Onshore wind project GI-111, Douglas County
Onshore wind
150 MWWithdrawn / abandoned Douglas, MOSoutheast Nov 2022target 2026
Solar + storage project LGE-GIS-2022-007, Lincoln County
Solar + storage
150 MWWithdrawn / abandoned Lincoln, KYSoutheast Sep 2022target 2026
Solar + storage project IC-1030, Mitchell County
Solar + storage
150 MWWithdrawn / abandoned Mitchell, GASoutheast Mar 2022
Solar project IC-1033, Brooks County
Solar
150 MWWithdrawn / abandoned Brooks, GASoutheast Mar 2022
Solar project IC-1065, Escambia County
Solar
150 MWWithdrawn / abandoned Escambia, ALSoutheast Sep 2022
Solar + storage project IC-1031, Jasper County
Solar + storage
150 MWWithdrawn / abandoned Jasper, MSSoutheast Mar 2022target 2025
Solar + storage project 505, Franklin County
Solar + storage
146 MWWithdrawn / abandoned Franklin, TNSoutheast Jun 2022
Page 1 of 5

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)