United States βΊ Grid βΊ Interconnection queues βΊ Kentucky
BATTERY STORAGE Β· SOUTHEASTBattery storage project LGE-GIS-2022-010, Bell County
Battery storage project LGE-GIS-2022-010, Bell County is a 216 MW battery storage request withdrawn in the Southeast interconnection queue, in Bell County, Kentucky, connecting to Louisville Gas & Electric and Kentucky Utilities Energy.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2022 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- LGE-GIS-2022-010
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Louisville Gas & Electric and Kentucky Utilities Energy
- Connection point (POI)
- Pineville - Harlan #1 161 kV line
- Location
- Bell County, Kentucky
- Technology
- Other Storage: 216 MW
- Total requested
- 216 MW
- Service type
- NRIS and ERIS
- Queue status
- Withdrawn
- Entered queue
- 30 September 2022
- Proposed online date
- December 2030
Location
Marker shows the centre of Bell County; the queue data does not give exact sites.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem