Interconnection queue in Texas, SPP (2023 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown132,738 MW
Active in queue2,738 MW13 requests
Agreement signed520 MW4 requests
Withdrawn6615.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

13 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project GEN-2023-204, Morris County
Gas
915 MWIn study Morris, TXSPP Oct 2023target 2028
Battery storage project GEN-2022-139, Harrison County
Battery storage
300 MWIn study Harrison, TXSPP Feb 2023target 2030
Gas project GEN-2022-147, Hale County
Gas
203 MWIn study Hale, TXSPP Feb 20232025
Other project GEN-2023-059, Harrison County
Other
200 MWIn study Harrison, TXSPP Sep 2023target 2029
Battery storage project GEN-2023-SR8, Hansford County
Battery storage
200 MWAgreement signed Hansford, TXSPP Feb 2023target 2026
Solar + storage project GEN-2023-193, Harrison County
Solar + storage
175 MWIn study Harrison, TXSPP Oct 2023target 2028
Solar + storage project GEN-2022-111, Marion County
Solar + storage
150 MWIn study Marion, TXSPP Feb 2023target 2027
Solar project GEN-2023-GR5, Lamb County
Solar
150 MWAgreement signed Lamb, TXSPP Jul 2023target 2026
Solar project GEN-2023-120, Swisher County
Solar
130 MWIn study Swisher, TXSPP Oct 2023target 2030
Battery storage project GEN-2023-SR12, Cochran County
Battery storage
120 MWAgreement signed Cochran, TXSPP Feb 20232025
Solar project GEN-2023-241, Franklin County
Solar
93.0 MWIn study Franklin, TXSPP Oct 2023target 2029
Solar project GEN-2023-135, Bowie County
Solar
52.0 MWIn study Bowie, TXSPP Oct 2023target 2026
Battery storage project GEN-2023-SR9, Crosby County
Battery storage
50.0 MWAgreement signed Crosby, TXSPP Feb 2023target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)