United States β€Ί Grid β€Ί Interconnection queues β€Ί Nebraska

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Nebraska, SPP

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown23939.6 GW
Active in queue16.2 GW84 requests
Agreement signed4,803 MW28 requests
Withdrawn23939.6 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

239 requests Β· page 1 of 5
ProjectCapacityStatusLocationRegionQueuedOnline
Coal project GEN-2007-011N02, Lancaster County
Coal
600 MWWithdrawn / abandoned Lancaster, NESPP Mar 2007
Onshore wind project GEN-2021-007, Knox County
Onshore wind
600 MWWithdrawn / abandoned Knox, NESPP May 20212025
Solar project GEN-2018-045, Banner County
Solar
550 MWWithdrawn / abandoned Banner, NESPP May 20182021
Solar project GEN-2018-044, Antelope County
Solar
500 MWWithdrawn / abandoned Antelope, NESPP May 20182025
Onshore wind project GEN-2023-116, Keith County
Onshore wind
500 MWWithdrawn / abandoned Keith, NESPP Oct 2023target 2030
Solar project GEN-2019-007, Lancaster County
Solar
500 MWWithdrawn / abandoned Lancaster, NESPP Apr 2019target 2022
Onshore wind project GEN-2018-110, Nemaha County
Onshore wind
500 MWWithdrawn / abandoned Nemaha, NESPP Nov 2018target 2023
Onshore wind project GEN-2016-159, Stanton County
Onshore wind
428 MWWithdrawn / abandoned Stanton, NESPP Nov 2016target 2020
Gas project GEN-2020-024, Sarpy County
Gas
425 MWWithdrawn / abandoned Sarpy, NESPP Apr 20202023
Gas project GEN-2020-035, Cass County
Gas
425 MWWithdrawn / abandoned Cass, NESPP Apr 20202023
Onshore wind project GEN-2019-029, Keith County
Onshore wind
404 MWWithdrawn / abandoned Keith, NESPP Apr 20192024
Coal project GEN-2007-011N01, Lancaster County
Coal
400 MWWithdrawn / abandoned Lancaster, NESPP Mar 2007
Coal project GEN-2001-039N, Hall County
Coal
400 MWWithdrawn / abandoned Hall, NESPP Nov 2001
Solar project GEN-2018-066, Lancaster County
Solar
400 MWWithdrawn / abandoned Lancaster, NESPP Oct 2018target 2022
Onshore wind project GEN-2008-121N01, Saline County
Onshore wind
400 MWWithdrawn / abandoned Saline, NESPP Oct 2008
Coal project GEN-2001-040N, Dawson County
Coal
400 MWWithdrawn / abandoned Dawson, NESPP Jan 2002
Onshore wind project GEN-2018-119, Johnson County
Onshore wind
400 MWWithdrawn / abandoned Johnson, NESPP Nov 2018target 2023
Onshore wind project GEN-2018-046, Banner County
Onshore wind
400 MWWithdrawn / abandoned Banner, NESPP May 20182025
Solar project GEN-2019-028, Lincoln County
Solar
400 MWWithdrawn / abandoned Lincoln, NESPP Apr 20192025
Onshore wind project GEN-2016-106, Keith County
Onshore wind
400 MWWithdrawn / abandoned Keith, NESPP Nov 20162020
Gas project GEN-2007-030N, Buffalo County
Gas
350 MWWithdrawn / abandoned Buffalo, NESPP Jul 2007
Onshore wind project GEN-2016-116, Dixon County
Onshore wind
320 MWWithdrawn / abandoned Dixon, NESPP Nov 2016target 2019
Onshore wind project GEN-2015-042, Dixon County
Onshore wind
320 MWWithdrawn / abandoned Dixon, NESPP Oct 2015target 2017
Solar project GEN-2017-212, Cedar County
Solar
310 MWWithdrawn / abandoned Cedar, NESPP Nov 2017target 2021
Solar project GEN-2017-008, Nuckolls County
Solar
305 MWWithdrawn / abandoned Nuckolls, NESPP Apr 2017target 2019
Solar project GEN-2022-175, Clay County
Solar
305 MWWithdrawn / abandoned Clay, NESPP Feb 2023target 2026
Solar + storage project GEN-2020-036, Cass County
Solar + storage
303 MWWithdrawn / abandoned Cass, NESPP Apr 20202023
Gas project GEN-2020-040, Cass County
Gas
303 MWWithdrawn / abandoned Cass, NESPP Apr 20202023
Onshore wind project GEN-2018-068, Madison County
Onshore wind
302 MWWithdrawn / abandoned Madison, NESPP Oct 2018target 2027
Onshore wind project GEN-2018-017, Keith County
Onshore wind
302 MWWithdrawn / abandoned Keith, NESPP Apr 2018target 2020
Onshore wind project GEN-2022-200, Holt County
Onshore wind
300 MWWithdrawn / abandoned Holt, NESPP Feb 2023target 2027
Onshore wind project GEN-2021-058, Madison County
Onshore wind
300 MWWithdrawn / abandoned Madison, NESPP Apr 2021target 2026
Onshore wind project GEN-2021-044, Dundy County
Onshore wind
300 MWWithdrawn / abandoned Dundy, NESPP Apr 2021target 2026
Onshore wind project GEN-2018-042, Johnson County
Onshore wind
300 MWWithdrawn / abandoned Johnson, NESPP May 20182025
Onshore wind project GEN-2023-117, Keith County
Onshore wind
300 MWWithdrawn / abandoned Keith, NESPP Oct 2023target 2030
Solar project GEN-2022-198, Lancaster County
Solar
300 MWWithdrawn / abandoned Lancaster, NESPP Feb 2023target 2028
Solar project GEN-2024-349, Hall County
Solar
300 MWWithdrawn / abandoned Hall, NESPP Mar 2025target 2029
Onshore wind project GEN-2021-060, Lancaster County
Onshore wind
300 MWWithdrawn / abandoned Lancaster, NESPP Apr 2021target 2027
Onshore wind project GEN-2024-151, Cheyenne County
Onshore wind
300 MWWithdrawn / abandoned Cheyenne, NESPP Mar 2025target 2030
Onshore wind project GEN-2024-150, Cheyenne County
Onshore wind
294 MWWithdrawn / abandoned Cheyenne, NESPP Mar 2025target 2030
Onshore wind project GEN-2022-188, Banner County
Onshore wind
290 MWWithdrawn / abandoned Banner, NESPP Feb 2023target 2026
Onshore wind project GEN-2017-165, Holt County
Onshore wind
288 MWWithdrawn / abandoned Holt, NESPP Nov 2017target 2020
Onshore wind project GEN-2022-050, Dawson County
Onshore wind
272 MWWithdrawn / abandoned Dawson, NESPP Jun 20222025
Solar project GEN-2022-077, Chase County
Solar
255 MWWithdrawn / abandoned Chase, NESPP Sep 2022target 2026
Onshore wind project GEN-2017-138, Holt County
Onshore wind
252 MWWithdrawn / abandoned Holt, NESPP Nov 2017target 2020
Onshore wind project GEN-2017-139, Holt County
Onshore wind
252 MWWithdrawn / abandoned Holt, NESPP Nov 2017target 2020
Onshore wind project GEN-2024-152, Cheyenne County
Onshore wind
250 MWWithdrawn / abandoned Cheyenne, NESPP Mar 2025target 2030
Onshore wind project GEN-2023-133, Custer County
Onshore wind
250 MWWithdrawn / abandoned Custer, NESPP Oct 2023target 2030
Coal project GEN-2001-029N1, Adams County
Coal
250 MWWithdrawn / abandoned Adams, NESPP Sep 2001
Onshore wind project GEN-2018-083, Madison County
Onshore wind
250 MWWithdrawn / abandoned Madison, NESPP Nov 2018target 2027
Page 1 of 5

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)