United States β€Ί Grid β€Ί Interconnection queues β€Ί Montana

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Montana, SPP

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown122,303 MW
Active in queue535 MW4 requests
Agreement signed310 MW3 requests
Withdrawn122,303 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

12 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GEN-2022-097, Rosebud County
Onshore wind
400 MWWithdrawn / abandoned Rosebud, MTSPP Oct 2022target 2027
Solar project GEN-2022-219, Dawson County
Solar
350 MWWithdrawn / abandoned Dawson, MTSPP Mar 2023target 2026
Onshore wind project GEN-2017-109, Dawson County
Onshore wind
321 MWWithdrawn / abandoned Dawson, MTSPP Aug 2017target 2020
Onshore wind project GEN-2024-224, Rosebud County
Onshore wind
261 MWWithdrawn / abandoned Rosebud, MTSPP Mar 2025target 2030
Onshore wind project GEN-2024-223, Dawson County
Onshore wind
241 MWWithdrawn / abandoned Dawson, MTSPP Mar 2025target 2030
Onshore wind project GEN-2017-237, Roosevelt County
Onshore wind
150 MWWithdrawn / abandoned Roosevelt, MTSPP Nov 2017target 2023
Solar project GEN-2019-043, Fallon County
Solar
150 MWWithdrawn / abandoned Fallon, MTSPP May 20192023
Onshore wind project GEN-2016-105, Dawson County
Onshore wind
120 MWWithdrawn / abandoned Dawson, MTSPP Nov 2016target 2019
Onshore wind project GEN-2015-098, Wibaux County
Onshore wind
100 MWWithdrawn / abandoned Wibaux, MTSPP Oct 2015target 2017
Solar + storage project GEN-2023-074, Rosebud County
Solar + storage
85.0 MWWithdrawn / abandoned Rosebud, MTSPP Oct 2023target 2028
Solar project GEN-2021-003, Richland County
Solar
75.5 MWWithdrawn / abandoned Richland, MTSPP Dec 20202024
Battery storage project GEN-2019-024, Wibaux County
Battery storage
50.0 MWWithdrawn / abandoned Wibaux, MTSPP May 2019target 2023

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)