United States βΊ Grid βΊ Interconnection queues βΊ Montana
ONSHORE WIND Β· SPPOnshore wind project GEN-2017-237, Roosevelt County
Onshore wind project GEN-2017-237, Roosevelt County is a 150 MW onshore wind request withdrawn in the SPP interconnection queue, in Roosevelt County, Montana, connecting to BEPC.
Queue statusWithdrawn / abandoned
- PlanningQueued Nov 2017 (completed)
- Withdrawn / abandonedSep 2022 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2017-237
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- BEPC
- Connection point (POI)
- Snake Butte 115kV Substation
- Location
- Roosevelt County, Montana
- Technology
- Wind: 150 MW
- Total requested
- 150 MW
- Service type
- Energy only (ERIS)
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 30 November 2017
- Proposed online date
- September 2023
- Withdrawn
- September 2022
Location
Marker shows the centre of Roosevelt County; the queue data does not give exact sites.
Other requests in Roosevelt County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem