Interconnection queue in Arkansas, SPP

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown152,085 MW
Active in queue2,085 MW15 requests
Agreement signed633 MW5 requests
Withdrawn397,303 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

15 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project GEN-2024-226, Hempstead County
Solar
300 MWIn study Hempstead, ARSPP Mar 2025target 2030
Solar project GEN-2021-033, Franklin County
Solar
204 MWAgreement signed Franklin, ARSPP May 2021target 2028
Solar project GEN-2021-036, Little River County
Solar
204 MWAgreement signed Little River, ARSPP May 2021target 2027
Battery storage project GEN-2022-130, Sebastian County
Battery storage
200 MWIn study Sebastian, ARSPP Feb 2023target 2030
Battery storage project GEN-2024-227, Hempstead County
Battery storage
200 MWIn study Hempstead, ARSPP Mar 2025target 2030
Solar + storage project GEN-2024-114, Jackson County
Solar + storage
199 MWIn study Jackson, ARSPP Mar 2025target 2028
Solar + storage project ERAS-2025-005, Yell County
Solar + storage
150 MWIn study Yell, ARSPP Sep 2025target 2029
Solar project GEN-2023-132, Craighead County
Solar
150 MWIn study Craighead, ARSPP Oct 2023target 2028
Gas project GEN-2024-003, Franklin County
Gas
102 MWIn study Franklin, ARSPP Apr 20242025
Solar project GEN-2018-064, Benton County
Solar
80.0 MWAgreement signed Benton, ARSPP Oct 2018target 2027
Solar project GEN-2017-231, Franklin County
Solar
72.5 MWAgreement signed Franklin, ARSPP Nov 2017target 2027
Battery storage project GEN-2024-SR2, Franklin County
Battery storage
72.5 MWAgreement signed Franklin, ARSPP Feb 2024target 2027
Battery storage project GEN-2024-243, Crawford County
Battery storage
50.1 MWIn study Crawford, ARSPP Mar 2025target 2029
Battery storage project GEN-2023-206, Sebastian County
Battery storage
50.0 MWIn study Sebastian, ARSPP Oct 2023target 2029
Solar project GEN-2024-312, Franklin County
Solar
50.0 MWIn study Franklin, ARSPP Mar 2025target 2030

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)