SOLAR · SPPSolar project GEN-2018-064, Benton County
Solar project GEN-2018-064, Benton County is a 80.0 MW solar request with a signed interconnection agreement in the SPP interconnection queue, in Benton County, Arkansas, connecting to GRDA.
Queue statusConsented
- PlanningQueued Oct 2018 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Jul 2027 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- GEN-2018-064
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- GRDA
- Connection point (POI)
- Tonnece Substation 69kV
- Location
- Benton County, Arkansas
- Technology
- Solar: 80.0 MW
- Total requested
- 80.0 MW
- Service type
- NRIS and ERIS
- Study phase
- IA FULLY EXECUTED/ON SCHEDULE
- Queue status
- Active
- Entered queue
- 24 October 2018
- Proposed online date
- July 2027
Location
Marker shows the centre of Benton County; the queue data does not give exact sites.
Other requests in Benton County
- Battery storage project GEN-2023-235, Benton CountyBattery storage · 250 MW · withdrawn
- Solar project GEN-2022-058, Benton CountySolar · 180 MW · withdrawn
- Onshore wind project GEN-2008-012, Benton CountyOnshore wind · 150 MW · withdrawn
- Battery storage project GEN-2023-213, Benton CountyBattery storage · 100 MW · withdrawn
- Battery storage project GEN-2023-232, Benton CountyBattery storage · 90.0 MW · withdrawn
- Solar + storage project GEN-2022-099, Benton CountySolar + storage · 80.0 MW · withdrawn
- Solar project GEN-2017-076, Benton CountySolar · 52.2 MW · withdrawn
- Onshore wind project GEN-2010-025, Benton CountyOnshore wind · 20.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem