United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in PJM (Mid-Atlantic, Midwest) (2015 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown675,685 MW
Active in queue2,928 MW7 requests
Agreement signed2,680 MW6 requests
Withdrawn23127.2 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

67 requests Β· page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Three Rivers Energy Center
Gas
1,160 MWOperating Grundy, ILPJM Oct 20152023
Indeck Niles Energy Center
Gas
994 MWOperating Cass, MIPJM Apr 20152021
Shawville Generating Station
Gas
590 MWOperating Clearfield, PAPJM Oct 20152016
Hilltop Energy Center Facility
Gas
515 MWOperating Greene, PAPJM Apr 20152021
Birdsboro Power LLC Generation Facility
Gas
450 MWOperating Berks, PAPJM Apr 20152019
Meadow Lake Wind Farm VI
Onshore wind
200 MWOperating White, INPJM May 20152018
Lordstown Energy Center
Gas
140 MWOperating Trumbull, OHPJM Jun 20152018
Hillcrest Solar Facility
Solar
125 MWOperating Brown, OHPJM Jun 20152020
Oak Solar
Solar
120 MWOperating Northampton, NCPJM Nov 20152024
Newsoms Solar
Solar
100 MWOperating Southampton, VAPJM Mar 20152017
Sunbury Generation Facility
Gas
97.0 MWOperating Snyder, PAPJM Apr 20152018
Ablemarle Beach Solar
Solar
80.0 MWOperating Washington, NCPJM Apr 20152020
Harts Mill Solar
Solar
80.0 MWOperating Edgecombe, NCPJM Sep 20152020
Gutenberg Solar
Solar
74.9 MWOperating Northampton, NCPJM Feb 20152019
Chestnut Solar
Solar
66.0 MWOperating Halifax, NCPJM Feb 20152019
Beech Ridge Wind Farm
Onshore wind
50.6 MWOperating Greenbrier, WVPJM Oct 20152020
Fayette Energy Facility
Gas
45.0 MWOperating Fayette, PAPJM Apr 20152017
Washington Energy Facility
Gas
45.0 MWOperating Washington, OHPJM Apr 20152016
Cornu
Gas
45.0 MWOperating Lawrence, OHPJM Apr 20152016
Cornu
Gas
45.0 MWOperating Lawrence, OHPJM Apr 20152016
Smithton Generating Station
Gas
40.0 MWOperating Westmoreland, PAPJM Oct 20152018
St. Joseph's Energy Center, LLC
Gas
40.0 MWOperating St. Joseph, INPJM Sep 20152018
Gas project AB1-181, Fluvanna County
Gas
37.3 MWOperating Fluvanna, VAPJM Oct 20152017
Liberty Electric
Gas
35.0 MWOperating Delaware, PAPJM Apr 20152017
Smith Mountain Hydro
Hydro
34.0 MWOperating Henry, VAPJM Feb 20152018
Bear Garden Facility
Gas
32.2 MWOperating Buckingham, VAPJM Apr 20152016
Possum Point Unit 6
Gas
28.0 MWOperating Prince William, VAPJM Mar 20152016
Mechanicsville Solar
Solar
20.0 MWOperating Hanover, VAPJM Jul 20152020
St. Thomas Township Solar Facility II
Solar
20.0 MWOperating Franklin, PAPJM Oct 20152020
Hilltop Energy Center Facility
Gas
20.0 MWOperating Greene, PAPJM Oct 20152021
Atlantic-RedBank 34.5kV Solar
Solar
20.0 MWOperating Monmouth, NJPJM Apr 20152019
St. Thomas Township Solar Facility
Solar
20.0 MWOperating Franklin, PAPJM Oct 20152020
Legore Bridge Solar Center Facility
Solar
20.0 MWOperating Frederick, MDPJM Oct 20152025
Alpha Battery Storage Facility
Battery storage
20.0 MWOperating Warren, NJPJM Mar 20152019
Big Level Wind Farm
Onshore wind
20.0 MWOperating Potter, PAPJM Oct 20152019
Marengo Battery Storage
Battery storage
20.0 MWOperating Mchenry, ILPJM Apr 20152018
Wyalusing 34.5kV
Gas
19.9 MWOperating Bradford, PAPJM Apr 20152019
Meherrin Solar
Solar
19.8 MWOperating Greensville, VAPJM Oct 20152022
Meherrin Solar
Solar
19.8 MWOperating Greensville, VAPJM Oct 20152022
Pondtown Solar 1
Solar
19.8 MWOperating Queen Anne's, MDPJM Oct 20152022
Pondtown Solar 1
Solar
19.8 MWOperating Queen Anne's, MDPJM Oct 20152022
Warren Natural Gas Generation Faciility
Gas
16.5 MWOperating Trumbull, OHPJM Jun 20152016
Biggs Ford Solar Facility
Solar
15.0 MWOperating Frederick, MDPJM Oct 20152025
Gavin #1
Coal
11.0 MWOperating Gallia, OHPJM Aug 20152017
Lakehurst Solar Farm
Solar
9.6 MWOperating Ocean, NJPJM Oct 20152020
Chestnut Solar
Solar
8.9 MWOperating Halifax, NCPJM Apr 20152019
Union Bridge Solar Facility
Solar
8.2 MWOperating Carroll, MDPJM Oct 20152022
Roy Road Battery Storage Facility
Battery storage
8.0 MWOperating Sussex, NJPJM Feb 20152023
Lakewood-Farmingdale Road Storage Facility
Battery storage
7.0 MWOperating Monmouth, NJPJM Feb 20152023
Lumberton Solar
Solar
6.8 MWOperating Burlington, NJPJM Jul 20152016
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)