πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Ohio

COAL Β· PJM

Gavin #1

Gavin #1 is a 11.0 MW coal request built and operating in the PJM interconnection queue, in Gallia County, Ohio, connecting to AEP.

Queue statusOperating
  1. PlanningQueued Aug 2015 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingDec 2017 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
AB1-058
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Gavin Unit #1 765kV
Location
Gallia County, Ohio
Technology
Coal: 11.0 MW
Total requested
11.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
Queue status
Operational
Entered queue
31 August 2015
Proposed online date
December 2017
Came online
December 2017

Location

Marker shows the centre of Gallia County; the queue data does not give exact sites.

Power plants in Ohio Β· Transmission lines in Ohio

Other requests in Gallia County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem