United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in ISO-NE (New England) (2015 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown16772 MW
Active in queue1.4 MW1 requests
Agreement signed1.4 MW1 requests
Withdrawn467,500 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

16 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Kendall Revised Reconfiguration Project
Gas
250 MWOperating Middlesex, MAISO-NE Oct 2015target 2016
Millinocket Frequency Conversion
Hydro
126 MWOperating Penobscot, MEISO-NE Feb 2015target 2019
Farminton Solar
Solar
78.4 MWOperating Franklin, MEISO-NE Aug 2015target 2021
CPV Towantic Increase
Gas
55.5 MWOperating New Haven, CTISO-NE Mar 2015target 2018
Sanford Airport Solar
Solar
50.0 MWOperating York, MEISO-NE Dec 2015target 2020
Lake Road Upgrades
Gas
49.8 MWOperating Windham, CTISO-NE Feb 2015target 2018
Combined Cycle Uprate #2
Gas
30.0 MWOperating Worcester, MAISO-NE Feb 2015target 2018
Antrim Wind
Onshore wind
28.4 MWOperating Hillsborough, NHISO-NE Mar 2015target 2019
Tiverton Power LLC Upgrade
Gas
21.5 MWOperating Newport, RIISO-NE Feb 2015target 2016
Nutmeg Solar, LLC
Solar
19.9 MWOperating Hartford, CTISO-NE Jun 2015target 2020
Coolidge Solar
Solar
19.9 MWOperating Windsor, VTISO-NE Sep 2015target 2018
Milford Upgrades - Phase I
Gas
16.6 MWOperating New Haven, CTISO-NE Feb 2015target 2017
Casco Bay Energy Storage
Battery storage
16.2 MWOperating Cumberland, MEISO-NE Nov 2015target 2016
Holiday Hill Community Wind
Onshore wind
5.0 MWOperating Hampden, MAISO-NE Feb 2015target 2020
Proctor Hydroelectric Station Uprate
Hydro
3.2 MWOperating Rutland, VTISO-NE Mar 2015target 2015
Kendall Reconfiguration Project
Gas
1.9 MWOperating Middlesex, MAISO-NE Jan 2015target 2016

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)