United States β€Ί Grid β€Ί Interconnection queues β€Ί California

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in California, CAISO

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,050551.7 GW
Active in queue148.9 GW376 requests
Agreement signed81.1 GW213 requests
Withdrawn2,050551.7 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,050 requests Β· page 1 of 41
ProjectCapacityStatusLocationRegionQueuedOnline
Cuatro Vientos
Wind + storage
3,527 MWWithdrawn / abandoned CACAISO Apr 2023target 2030
Edgewood Solar Hybrid
Solar + storage
3,400 MWWithdrawn / abandoned Fresno, CACAISO Apr 2020target 2024
Chokecherry and Sierra Madre Wind Energy Project
Onshore wind
3,290 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Pinebrook Solar Hybrid Energy Center
Solar + storage
3,074 MWWithdrawn / abandoned Fresno, CACAISO Apr 2019target 2024
Eternal 2
Other
2,851 MWWithdrawn / abandoned Riverside, CACAISO Apr 2021target 2031
Eternal Pumped Storage
Other
2,807 MWWithdrawn / abandoned Riverside, CACAISO Apr 2020target 2026
Ventura Wind
Onshore wind
2,482 MWWithdrawn / abandoned CACAISO Apr 2023target 2030
Monterey Wind
Onshore wind
2,462 MWWithdrawn / abandoned CACAISO Apr 2023target 2030
Oaks Wind
Onshore wind
2,460 MWWithdrawn / abandoned CACAISO Apr 2023target 2030
Charlie Wind
Onshore wind
2,460 MWWithdrawn / abandoned CACAISO Apr 2023target 2030
Boson
Solar + storage
2,347 MWWithdrawn / abandoned Kern, CACAISO Apr 2023target 2028
Islay
Wind + storage
2,275 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2021target 2034
Atlas
Solar + storage
2,074 MWWithdrawn / abandoned Fresno, CACAISO Apr 2018target 2022
Gemini Wind North
Onshore wind
2,006 MWWithdrawn / abandoned CACAISO Apr 2018target 2025
Alamitos Energy Center
Gas
1,903 MWWithdrawn / abandoned Los Angeles, CACAISO Apr 2012target 2025
Vinson Energy
Wind + storage
1,887 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2020target 2027
Nimitz 2 Generation
Wind + storage
1,887 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2019target 2026
Intrepid Energy
Wind + storage
1,887 MWWithdrawn / abandoned Humboldt, CACAISO Apr 2020target 2027
Nimitz 1 Generation
Wind + storage
1,887 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2019target 2024
Tempest Generation
Wind + storage
1,887 MWWithdrawn / abandoned Humboldt, CACAISO Apr 2019target 2025
Seawolf Generation
Wind + storage
1,887 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2019target 2024
Ethan Creek
Onshore wind
1,870 MWWithdrawn / abandoned CACAISO Apr 2023target 2030
Porthos Solar
Solar + storage
1,800 MWWithdrawn / abandoned Riverside, CACAISO Apr 2018target 2022
Empire
Battery storage
1,647 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2021target 2024
Gema Hybrid
Solar + storage
1,547 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Two Bunch Palms
Battery storage
1,518 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Salinan Energy
Wind + storage
1,509 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2021target 2032
Bravo Wind
Offshore wind
1,465 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2021target 2034
Lighthouse Wind
Offshore wind
1,456 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2020target 2027
Eagle Mountain Pump Storage #4
Battery storage
1,408 MWWithdrawn / abandoned Riverside, CACAISO Apr 2015target 2022
Iron Hills Pumped Storage
Battery storage
1,407 MWWithdrawn / abandoned Riverside, CACAISO Apr 2018target 2025
Eagle Mountain Pump Storage #3
Hydro
1,400 MWWithdrawn / abandoned Riverside, CACAISO Mar 2011target 2017
Eagle Mountain Pump Storage #2
Hydro
1,400 MWWithdrawn / abandoned Riverside, CACAISO Feb 2010target 2016
Ses Solar Six
Solar
1,400 MWWithdrawn / abandoned San Bernardino, CACAISO Jun 2006target 2013
Southern Sierra PSP
Other
1,392 MWWithdrawn / abandoned CACAISO Apr 2023target 2030
Helms PSP Uprate
Battery storage
1,392 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Eagle Mountain Pumped Storage Project
Hydro
1,300 MWWithdrawn / abandoned Riverside, CACAISO May 2008target 2014
White Hills Solar Project
Solar + storage
1,278 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Borderline Solar
Solar + storage
1,268 MWWithdrawn / abandoned Inyo, CACAISO Apr 2023target 2028
Una Lake Solar
Solar + storage
1,243 MWWithdrawn / abandoned Los Angeles, CACAISO Apr 2019target 2022
Magic Valley Wind 1
Wind + storage
1,239 MWWithdrawn / abandoned CACAISO Apr 2023target 2026
Colima Hybrid Solar
Solar + storage
1,212 MWWithdrawn / abandoned Kern, CACAISO Apr 2021target 2026
Redwood Coast Offshore Wind 2
Offshore wind
1,206 MWWithdrawn / abandoned CACAISO Apr 2023target 2030
Redwood Coast Offshore Wind 1
Offshore wind
1,206 MWWithdrawn / abandoned CACAISO Apr 2023target 2030
Whispering Sands Solar
Solar + storage
1,202 MWWithdrawn / abandoned CACAISO Apr 2023target 2026
Morro Bay Modernization Project
Gas
1,200 MWWithdrawn / abandoned San Luis Obispo, CACAISO Dec 2000target 2008
Ses Solar Seven
Solar
1,200 MWWithdrawn / abandoned San Bernardino, CACAISO Aug 2006target 2011
Herculean
Solar + storage
1,198 MWWithdrawn / abandoned CACAISO Apr 2023target 2031
Meson
Solar + storage
1,191 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
MidBishop Energy Storage
Battery storage
1,191 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Page 1 of 41

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)